This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
11 units
Floors
17
Buildings
2
Parking
1 spaces
Land area
436 sq m
Sanctioned built-up
1,747 sq m

Timeline

RERA registeredDec 2022
Proposed completionApr 2026
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

Sugee Twenty Three Developers LLP

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2022–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
GNorth-400028
Taluka
Ward GNorth
District
Mumbai City
Pincode
400028
Survey no.
1741
North boundary
Plot No 30
East boundary
40 Feet Road
South boundary
50 Feet Road
West boundary
Plot No 32
What’s nearby
Schools2 schools within 500m · 11 educational institutions within 1km · College or university 175m away
HealthcareHospital 294m away · 14 clinics within 1km · Pharmacy within 1km
Lifestyle1 park within 500m · Gym or sports centre 168m away · 38+ restaurants and cafes within 1km
ShoppingSupermarket 793m away · Mall 1.3km away · Convenience store within 500m
Getting around
Expressway 1.4 km · Dr Babasaheb Ambedkar Marg (Vincent Road)Primary road 184 m · Lady Jamshedji RoadRailway line 734 mMetro station 563m away (Dadar)9 bus stops within 500m
Water & environment
Water body 1.7 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 1741

The promised possession date (30 Apr 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,284 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,560 projects the radar draws within 6 km — every kind, every stage — 551 are residential projects still under way. This list keeps only those, and looks further out.

63 projects within 1 km — showing the nearest 6.

30 m awayResidential / Group Housing

DIPTI OPAL BAY

DIPTI ASSOCIATES · DADAR WEST

Aug 2025registered
Dec 2029target completion
Scale37 flatsAuthorityMahaRERA
90 m awayResidential / Group Housing

SAFFRON

BUILDARCH - GP · DADAR WEST

Jun 2025registered
Dec 2028target completion
Scale31 flatsAuthorityMahaRERA
140 m awayResidential / Group Housing

PARK VIEW RESIDENCY

SHAGUN INFRASTRUCTURE · Mumbai City

Jan 2026registered
Dec 2028target completion
Scale32 flatsAuthorityMahaRERA
170 m awayOthers

Viyaara Altiora

STRUCTURE CREATORS · Mahim West · Ward GNorth

Mar 2025registered
Dec 2029target completion
Scale92 flatsAuthorityMahaRERA
170 m awayResidential / Group Housing

Harsh Crown

HARSH DEVELOPERS & INFRASTRUCTURE LLP · Mahim · Mumbai City

Mar 2026registered
May 2029target completion
Government Guidance Rate₹2,95,872/sq ydScale24 flatsAuthorityMahaRERA
180 m awayResidential / Group Housing

Shree Krishnakunj

Sugee Developers Private Limited · Mumbai City

Oct 2025registered
Nov 2028target completion
Scale19 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.