SERENORA WING A

P52100066561 · MahaRERA · https://gethorizon.in/projects/serenora-wing-a-bhugaon-mulshi-16rdju22

01

Complete project overview

MahaRERA · Registration filing
Units
35 units
Floors
9
Buildings
2
Parking
82 spaces
Land area
1,520 sq m
Sanctioned built-up
3,168 sq m

Timeline

RERA registeredJun 2024
Proposed completionDec 2027
TodaySep 2026
Construction progress
Podiums0%
Superstructure0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Storm Water Drains10%
Community Building…10%
Stairs & lifts20%
OC-readiness20%
Internal Roads & F…20%
Water Supply20%
Flat fit-out50%
Internal finishes60%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
External finishes100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

NIRMITEE UNICONS INFRA LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhugaon
Taluka
Mulshi
District
Pune
Pincode
412115
Survey no.
271/10
North boundary
by s no 271 part
East boundary
by s no 271 part
South boundary
Approach Road
West boundary
by s no 271 part
What’s nearby
SchoolsNo schools within 2km · College or university 1.5km away
HealthcareNearest hospital 2.7km away
LifestyleNo parks within 2km · Gym or sports centre 1.5km away · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Bank 398m away
Getting around
Expressway 2.1 km · Katraj - Dehu Road BypassPrimary road 142 m · Paud RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 86 m · RamnadiWater body 773 m · CP Chondhe Lake
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. 271/10
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,105 residential projects still under way within 25 km. Step out ring by ring:

Of the 719 projects the radar draws within 6 km — every kind, every stage — 251 are residential projects still under way. This list keeps only those, and looks further out.

25 projects within 1 km — showing the nearest 6.

100 m awayResidential / Group Housing

River Crest

ARP Developers · Bhugaon · Mulshi

Nov 2024registered
Dec 2028target completion
Scale64 flatsAuthorityMahaRERA
140 m awayResidential / Group Housing

Kumar Prakruti

Kumar Properties Govind Shree Realtors LLP · Bhugaon · Mulshi

Dec 2023registered
Oct 2026target completion
Scale59 flatsAuthorityMahaRERA
220 m awayMixed

C P SHINE

T AND P DEVELOPERS · Bhugaon · Mulshi

Oct 2025registered
Aug 2029target completion
Scale18 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

PWC Towers Hill Side Phase III

Enerrgia Skyi Developers · Bhugaon · Mulshi

May 2024registered
Aug 2028target completion
Scale75 flatsAuthorityMahaRERA
400 m awayResidential / Group Housing

The Pwc Towers Phase I

Badamikar Realities Pvt Ltd · Bhugaon · Mulshi

Dec 2022registered
Dec 2026target completion
Scale96 flatsAuthorityMahaRERA
530 m awayResidential / Group Housing

SOMMET

SANKLA BUILDCOON · Bhugaon · Mulshi

Oct 2020registered
Jun 2026target completion
Scale156 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.