HORIZON
Share

HORIZONSearch & explore India’s real estate — the whole picture. gethorizon.in1.2 lakh+ projects · 78k+ builders · 600+ micro-markets · across 22 states
Detailed Report

SHIVAM - Embrace Azure Living -

P51900076901 · MahaRERA · https://gethorizon.in/projects/shivam-embrace-azure-living-gnorth-400028-ward-gnorth-b5j04u4s

01

Complete project overview

MahaRERA · Registration filing
Units
16 units
Floors
22
Buildings
2
Parking
63 spaces
Land area
525 sq m
Sanctioned built-up
1,731 sq m

Timeline

RERA registeredJul 2024
Proposed completionDec 2027
TodaySep 2026
Construction progress
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Superstructure25%
Podiums90%
Basement (if any)97%
Stilt floor98%
Excavation100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Shivruddhi Dreams LLP

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
The Horizon Radar(within 6 km)
2km4km6kmN
  • This project
  • 152 new projects last year
  • 1,268 nearby projects
≈ locality centre · geocoded, verified · 19.0216, 72.8338 · © OpenStreetMap contributors
Village
GNorth-400028
Taluka
Ward GNorth
District
Mumbai City
Pincode
400028
Survey no.
1168
North boundary
Dadar Gurudev CHS
East boundary
Dadar Jivan CHS
South boundary
Kashinath Dhuru Road
West boundary
Arvind Hari Raut Marg
What’s nearby
Schools1 school within 500m · 8 educational institutions within 1km · College or university 259m away
HealthcareHospital 151m away · 10 clinics within 1km · Pharmacy within 1km
LifestylePark 581m away · Gym or sports centre 617m away · 37+ restaurants and cafes within 1km
ShoppingSupermarket 319m away · Mall 328m away · Bank 345m away
Getting around
Expressway 1.4 kmPrimary road 337 m · Raobahadur S.K. Bole MargRailway line 978 mMetro station 609m away (Dadar)12 bus stops within 500m
Water & environment
Water body 1.0 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 1168
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projects — about 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market — 100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA→

07

Other projects nearby

The register · within 25 km

3,131 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,268 projects the radar draws within 6 km — every kind, every stage — 472 are residential projects still under way. This list keeps only those, and looks further out.

43 projects within 1 km — showing the nearest 6.

Mumbai CityResidential / Group Housing

Sugee Sukrut

Sugee Nine Developers LLP

Jun 2023registered
Oct 2026target completion
Scale24 flatsAuthorityMahaRERA
GNorth-400028Others

MANSION 835

Rajadhiraj Construction LLP

Jun 2024registered
Dec 2027target completion
Scale22 flatsAuthorityMahaRERA
Mumbai CityResidential / Group Housing

BUILDARCH SAKURA

BUILDARCH LAND DEVLOPERS PVT. LTD.

Apr 2024registered
Dec 2026target completion
Scale28 flatsAuthorityMahaRERA
GNorth-400028Residential / Group Housing

Janai Heritage

S N Bandekar & Associates

Mar 2026registered
Sep 2029target completion
Scale99 flatsAuthorityMahaRERA
GNorth-400028Others

Pearl Bay View

PEARL CONCEPT CONSTRUCTIONS

Oct 2022registered
Dec 2026target completion
Scale36 flatsAuthorityMahaRERA
GNorth-400028Residential / Group Housing

Eterna 275

ETERNA LIFESPACE LLP

Mar 2026registered
Dec 2029target completion
Scale32 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.

Sources

Where each section of this report comes from.

  1. 01Complete project overview
    • The project's registration filing with MahaRERA, as the builder submitted it.
  2. 02Builder's track record
    • MahaRERA: the builder's registration.
    • The track record: every project filed under this builder, counted by Horizon across the state RERA registers it holds.
  3. 03Location
    • Address and pincode: the MahaRERA filing.
    • Coordinates: geocoded by Horizon from the filed address with Google Geocoding, matched to the locality centre, not the exact site.
    • What's nearby and getting around: distances measured by Horizon on OpenStreetMap data, © OpenStreetMap contributors (ODbL). Not from the RERA filing.
    • The Horizon Radar: the RERA-registered projects Horizon holds within 6 km of these coordinates.
    • Map: © OpenStreetMap contributors (ODbL).
  4. 04Government Guidance Rate
    • No government guidance rate could be matched to this project from Maharashtra's published schedules.
  5. 05Planning authority
    • MahaRERA: the approved building plan, as filed.
    • The approving body's other projects: counted by Horizon across the register.
  6. 06Complaints & litigation
    • MahaRERA's public record lists no complaints or litigation for this project.
  7. 07Other projects nearby
    • The RERA-registered projects Horizon holds within 25 km of these coordinates.

Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/shivam-embrace-azure-living-gnorth-400028-ward-gnorth-b5j04u4s.

Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.