Complete project overview

K-RERA · Registration filing
Units
77 units
Mix
11 × TYPE A 3BHK · 11 × TYPE B 3BHK · 11 × TYPE C 2BHK · 11 × TYPE D 3BHK · 11 × TYPE E 3BHK · 11 × TYPE F 2BHK
Booked
77 of 77 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,916 sq m
Floor area
13,019 sq m
Description
SKYLINE PIXEL

Timeline

Project startedNov 2020
RERA registeredMay 2021
Proposed completionAug 2024
TodayJul 2026
Construction progress

67% overall, as filed

Stilt Floor0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
The external plumbing and external plastering70%
Completion of terraces floor each building70%
Sanitary Fittings75%
Electrical Fittings75%
Installation of lifts, water pumps etc75%
Fire Fighting Fittings and Equipment75%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc75%
Staircases, Lifts Wells77%
Overhead and Underground Water Tanks.77%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 77 available
TypeArea sq mAvailable
TYPE A 3BHK760 of 11
TYPE B 3BHK760 of 11
TYPE C 2BHK580 of 11
TYPE D 3BHK750 of 11
TYPE E 3BHK750 of 11
TYPE F 2BHK580 of 11
TYPE G 2BHK580 of 11

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

M/s Skyline Builders

PartnershipPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
30Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,397 homes · 125 plotson the public record across 30 projects
2,87,146 sq mbuilt-up filed
95,889 sq mplotted area
1,58,410 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Cochin Municipal CorporationMunicipal Corporation6 of 30 projects
Kozhikode Municipal CorporationMunicipal Corporation4 of 30 projects
Thrikkakara MunicipalityMunicipality4 of 30 projects
CorporationLocal body (LSGI)2 of 30 projects
Mangalapuram Grama PanchayatGrama Panchayat2 of 30 projects
MunicipalityLocal body (LSGI)this project2 of 30 projects
Thrissur Municipal CorporationMunicipal Corporation2 of 30 projects
Alanagd Grama PanchayatGrama Panchayat1 of 30 projects
Eloor MunicipalityMunicipality1 of 30 projects
Kannur Municipal CorporationMunicipal Corporation1 of 30 projects
Kottayam MunicipalityMunicipality1 of 30 projects
Municipal Corporation Of CochinLocal body (LSGI)1 of 30 projects
Tripunithura MunicipalityMunicipality1 of 30 projects
Viajayapuram Grama PanchayatGrama Panchayat1 of 30 projects
Vijayapuram Grama PanchayatGrama Panchayat1 of 30 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
LAVANYA NAGAR
Village
KAKKANAD
Taluk
Kanayannur
District
Ernakulam
Pincode
682030
Survey no.
100/15-12,100/15-13
Patta no.
8403
What’s nearby
SchoolsNearest school 1.4km away · Library 517m away
HealthcareHospital 647m away · 2 clinics within 1km · Pharmacy within 1km
LifestylePark 1.2km away · Gym or sports centre 1.2km away · 27+ restaurants and cafes within 1km
ShoppingSupermarket 14m away · Mall 1.6km away · Convenience store within 500m
Getting around
Expressway 4.5 km · Salem - Kochi - Kanyakumari RoadPrimary road 198 m · Ernakulam - Thekkady RoadRailway line 4.6 kmMetro station 1.5km away (InfoPark I Station)13 bus stops within 500m
Water & environment
Water body 593 mCanal 903 m · CANAL
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Municipality

Local body (LSGI)
approved 15 May 2020 · 6 yrs ago
Building Permit no. TP1-BA(10539)/2020Survey no. 100/15-12,100/15-13

The promised possession date (1 Aug 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan TP1-BA(10539)/2020 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Municipality

Local body

Has approved 7 RERA projects0.5% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
5
On record
370 flats · 0 plots
Reach
5 districts
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.