SPR CITY Market of India - Phase I

TN/29/Building/0416/2024 · TNRERA · https://gethorizon.in/projects/spr-city-market-of-india-phase-i-s0u9j8dj

01

Complete project overview

TNRERA · Registration filing
Description
Registration of Block No.6 (Commercial Market & Retail) Triple Basement Floor (1st Basement Partly Shops & Partly Parking, 2nd &3rd Basement for Parking use) + Ground Floor + 1st Floor to 4th Floor (Shops, Food Court & Multiplex) + 5th Floor ( Parking, Food Court & Multiplex) + 6th Floor to 7th Floor (Partly Shops & Partly Parking) + 8th Floor to 10th Floor (Partly Trade Office and Partly Parking) + 11th Floor Part to 15th Floor Part (Office use) comprised in R.S.No.218/2, 218/5, 219/1 to 6, 220/2 of Block No.11 and R.S.No.221/2, 222/1 & 2 of Block No.12, Perambur Town, Division 73, Zone VI, Purasaiwakkam - Perambur Taluk, within the limits of Greater Chennai Corporation, Chennai District.
Registration no.
TN/29/Building/0416/2024

Timeline

RERA registeredJul 2024
Proposed completionDec 2025
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

SPR CONSTRUCTION PRIVATE LIMITED

SPR CONSTRUCTION PRIVATE LIMITEDPromoter
3Projects
1Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3 projectson the public record across 3 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SPR CONSTRUCTION PRIVATE LIMITED— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
SchoolsNearest school 1.5km away · Library 1.5km away
HealthcareHospital 786m away · 4 clinics within 1km
LifestyleNo parks within 2km · Gym or sports centre 2.0km away
ShoppingSupermarket 756m away · Bank 749m away
Getting around
Primary road 144 m · Cooks RoadRailway line 709 mRailway station 850m away (Vyasarpadi Jeeva)4 bus stops within 500m
Water & environment
Water body 782 m
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

CMDA (Chennai Metropolitan Development Authority)

CMDA (Chennai Metropolitan Development Authority)
approved 11 Jul 2024 · 2 yrs ago
Planning Permission no. PP/HRB/01/2024

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan PP/HRB/01/2024 on the approving authority’s portal to confirm the approval.

The approving body, at scale

CMDA (Chennai Metropolitan Development Authority)

Metropolitan development authority

Has approved 1,914 RERA projectsabout 1 in 2 in Tamil Nadu, more than any other body in the state.

Builders
1,310
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

415 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 99 projects the radar draws within 6 km — every kind, every stage — 75 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

3 projects within 1 km — showing the nearest 3.

190 m away

SPR BINNY HILIVING - PHASE II

SPR CONSTRUCTION PRIVATE LIMITED

Jun 2024registered
Jun 2026target completion
AuthorityTNRERA
190 m away

SPR BINNY SKY - PHASE I (THE CAPITAL DISTRICT)

SPR CONSTRUCTION PRIVATE LIMITED

Jun 2024registered
Mar 2029target completion
AuthorityTNRERA
910 m away

RAJPARIS GALAXY

RAJPARIS RE-DEVELOPMENT AND CONSTRUCTIONS

Aug 2025registered
Dec 2027target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.