Complete project overview

GujRERA · Registration filing
Units
876 units
Mix
440 × Lig-Ii Flats · 208 × Mig-I Flats · 208 × Mig-Ii Flats
Carpet area
26–80 sq mper-unit range, as filed
Blocks
10
Parking
1 spaces
Land area
34,859 sq m
Affordable housing
Yes — registered under affordable housingprice caps & eligibility apply

Timeline

Project startedMay 2015
RERA registeredSep 2018
Proposed completionMar 2019
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

856 units across 3 batches
TypeArea sq mCount
Lig-Ii Flats45440
Mig-I Flats65208
Mig-Ii Flats80208

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

GUJARAT HOUSING BOARD

COMPETENT AUTHORITY/ GOVERNMENTPromoter type
Vadodara, GujaratBased in
37Projects
17Cities
2018–presentActive
Timelineevery project, start → promised completion
176 MIG + 28 SHOPS AT BHARUCH522 LIG KAILASHNAGAR476 LIG II + 244 MIG I + 44 SHOPS at sachin320 LIG 1 + 480 LIG 2 AT SACHIN IN PLOT B32 SHOPS + 476 LIG-1 + 400 LIG-2 + 120 MIG-1 AT SANAND162 MIG-I + 18 SHOPS, PLOT-B,PACKAGE-13, GORWA54 MIG-I + 334 LIG-II + 336 LIG-I +12 SHOPS at Plot-A, Phase-2, Package No.1348 SHOPS 896 LIG II 672 MIG I 336 MIG II68 SHOPS + 1228 LIG-2 + 432 MIG-1 AT GOTA139 LIG I + 352 LIG II + 64 MIG I + 68 SHOPS42 SHOPS + 548 MIG-1 AT PLOT B, GOTA168 LIG II + 56 MIG I + 42 SHOPS BUILDINGS572 LIG2+56 SHOPS AT TARSAMIYA BHAVNAGAR280 MIG 60 SHOPS56 LIG I 224 LIG II 56 MIG I 29 SHOPS440 LIG-II + 208 MIG-I + 208 MIG-II + 20 SHOPS AT PHASE-3, PACKAGE NO. 21, SAMTA , VADODARA192 Out of 256 EWS, Package-22, Phase-3, Mahemdabad42 LIG-1 + 72 LIG-2 + 12 MIG-1 at Dahegam12 SHOPS + 364 MIG I at Plot C & D Gota112 MIG 2 TN NARANPURA AHMEDABAD8 SHOPS + 392EWS-I + 224EWS-II at Hathijan64 OUT OF 256 EWS,PACKAGE-22,PHASE-3,MEHEMDABAD1552 LIG-II AND 69 SHOPS AT JAHANGIRABAD PHASE-V336 EWS-I AND 280 EWS-II AT CHHAPRABHATHA PHASE-V49 shops + 1560 EWS - II at Gorwa, Phase 5192 EWS I & 22 SHOPS AT HASANPAR WANKANER224 EWS 1 AT R21 TARSAMIYA BHAVNAGAR.160 EWS-1 AT R 24B TARSAMIYA BHAVNAGAR288 EWS 1 AT R20 TARSAMIYA BHAVNAGAR576 EWS 2 AT R 10A TARSAMIYA BHAVNAGAR896 EWS 1 AT R14 R15 R16 AT TARSAMIYA BHAVNAGAR192 EWS 2 AT 10B TARSAMIYA BHAVNAGAR160 EWS 1 + COMMERCIAL BUILDING AT TARSAMIYA BHAVNAGARPMAY EWS AT KESHOD PHASE 159 LIG (Residential) & Commercial (Mix type) of Gujarat Housing Board at Pandesara Phase-VDemonstration Housing Project at Ahmedabad19 Shops and 448 2 and 3 BHK Flats at Gorwa Phase 6
Builder DNAthe whole portfolio, summed
21,403 homeson the public record across 37 projects
3,44,751 sq mbuilt-up filed
7,37,617 sq mland declared
₹2009.23 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Bhavnagar Municipal CorporationMunicipal / Corporation9 of 37 projects
Ahmedabad Urban Development AuthorityUrban Development Authority6 of 37 projects
Ahmedabad Municipal CorporationMunicipal / Corporation4 of 37 projects
Vadodara Municipal CorporationMunicipal / Corporationthis project4 of 37 projects
Surat Municipal CorporationMunicipal / Corporation3 of 37 projects
Surat Urban Development AuthorityUrban Development Authority3 of 37 projects
Others2 of 37 projects
Bharuch- Ankleshwar Urban Development AuthorityUrban Development Authority1 of 37 projects
Bhuj Area Development AuthorityUrban Development Authority1 of 37 projects
Junagadh Municipal CorporationMunicipal / Corporation1 of 37 projects
Mahuva MunicipalityMunicipal / Corporation1 of 37 projects
Navsari MunicipalityMunicipal / Corporation1 of 37 projects
Wankaner MunicipalityMunicipal / Corporation1 of 37 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Vadodara
District
Vadodara
Pincode
390023
Address
NEAR SAMTA POLICE STATIONSAMTA ROAD
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 204m away · 6 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.6 kmPrimary road 1.1 km · Gotri RoadRailway line 2.4 kmRailway station 3.8km away (Vadodara Junction)Limited bus connectivity nearby
Water & environment
Water body 835 mCanal 1.7 km · Vadodara Branch Canal
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹141.76 Cr declared to build 876 flats. What that works out to:

₹5.13 Lakh – ₹25.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹16.18 Lakhdeclared cost per flatall-in — land + construction
0%of the cost is land₹8/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Vadodara Municipal Corporation

Municipal / Corporation
Building Permitapproved 5 Sep 2018 · 7 yrs ago

The promised possession date (31 Mar 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

1 of 10 blocks carry a Building-Use (BU) permission (latest 28 Jan 2019)— Gujarat’s legal-to-occupy sign-off. The remaining blocks are not shown as BU-cleared here; treat those as not-yet-occupiable until confirmed.

The approving body, at scale

Vadodara Municipal Corporation

Municipal Corporation

Has approved 1,372 RERA projectsabout 1 in 13 in Gujarat.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,133
On record
1,45,936 flats · 226 plots
Reach
4 talukas
Since
2006

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.