HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
6
Parking
58 spaces
Land area
1,795 sq m
Sanctioned built-up
4,966 sq m

Timeline

RERA registeredNov 2023
Proposed completionOct 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply90%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Water conservation…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

GAURAV LAND CORPORATION

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400615
Survey no.
OLD S.NO 50, NEW S.NO 61/4/1, S.NO 51/1
North boundary
20M wide ROAD
East boundary
PURNAIK CITY - M BUILDING
South boundary
PURANIK CITY - M BUILDING
West boundary
INTERNAL ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 265m away · 1 clinic within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 765m away · ATM within 500m
Getting around
Expressway 1.1 kmPrimary road 311 m · Kasarvadavali flyoverRailway line 3.3 kmMetro station 637m away (Gowniwada Station)5 bus stops within 500m
Water & environment
Water body 213 mRiver 366 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. OLD S.NO 50, NEW S.NO 61/4/1, S.NO 51/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.