Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
4
Land area
6,607 sq m
Sanctioned built-up
8,742 sq m
Recreational open space
583 sq m

Timeline

RERA registeredMar 2024
Proposed completionJun 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Excavation50%
Plinth50%
Superstructure86%
Stairs & lifts86%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

QUBA SQUARE LLP

PartnershipPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhiwandi (M Corp.)
Taluka
Bhiwandi
District
Thane
Pincode
421302
Survey no.
911, 912, 950 to 975 (S.No.70P & 71P)
North boundary
Layout Road
East boundary
End of Nala beside Baitussalam Masjid
South boundary
Middle of the Naigaon Road Opp Galaxy and Daimond
West boundary
Boundary Wall Of Hakim Seth Property
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 311m away · 3 clinics within 1km
LifestylePark 1.7km away
ShoppingNo supermarket within 2km
Getting around
Expressway 330 mPrimary road 538 mRailway line 4.4 kmRailway station 4.4km away (Bhivandi Road)2 bus stops within 500m
Water & environment
River 1.5 km · Kamvadi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Bhiwandi Nizampur City Municipal Corporation (Bncmc)

Municipal Corporation
Building Permit
Survey no. 911, 912, 950 to 975 (S.No.70P & 71P)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Bhiwandi Nizampur City Municipal Corporation (Bncmc)

Municipal corporation

Has approved 16 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
15
On record
36 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.