GODREJ TIARA
Godrej Properties Limited · Bengaluru North
B.M.MAGNOLIA PARK
Timeline
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.









₹644.17 Cr declared. What that works out to:
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
In Karnataka it’s called the guidance value.
No government guidance rate is shown for this project.
Karnataka's guidance-value gazettes are in Horizon's record, but this project's address doesn't name a place any of its sub-registrar's tables print.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
The promised possession date (31 Dec 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Has approved 2,111 RERA projects — about 1 in 4 in Karnataka, more than any other body in the state.
an apartments market — 100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.
More apartment-heavy than Karnataka overall — 100% apartments here vs 62% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
6 complaints · 6 disposed · 0 open
A disposed complaint may have been resolved for or against the builder, and only disputes escalated to RERA Karnataka appear here at all.
| Number | Date | Status | |
|---|---|---|---|
| 01523/2023 | Project Incomplete | 4 Oct 2023 | Disposed — authority bench 5 |
| 01230/2023 | Incomplete of Project | 8 Aug 2023 | Disposed — authority bench 5 |
| 01048/2023 | Delay of project completion | 3 Jul 2023 | Disposed — authority bench 5 |
| CMP/220321/0009170 | Expecting with project completion as per the Broucher and delay compensation. | 21 Mar 2022 | Disposed — authority bench 5 |
| CMP/220321/0009171 | Project work Stopped without any Aminities, Permanent power and OC/CC. | 21 Mar 2022 | Disposed — authority bench 5 |
| Number | Date | Status | |
|---|---|---|---|
| CMP/220314/0009120 | Project is Delayed, there is no OC, CC, Permanent Power and Ameneties as per the Agreement | 14 Mar 2022 | Disposed — authority bench 5 |
Only what the builder declared, or what RERA Karnataka records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Karnataka, or that this register doesn’t publish it — never that nothing happened.
855 residential projects still under way within 25 km. Step out ring by ring:
Of the 199 projects the radar draws within 6 km — every kind, every stage — 32 are residential projects still under way. This list keeps only those, and looks further out.
4 projects between 1 and 3 km — showing the nearest 4.
Godrej Properties Limited · Bengaluru North
KARNATAKA SLUM DEVELOPMENT BOARD · Kadur
Mahesh Govindaraju · Bengaluru North
VISTA SPACES SUN (CHAMPAKA) PRIVATE LIMITED · Bengaluru North
Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.
What this record cannot tell you
Where each section of this report comes from.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/b-m-magnolia-park-bengaluru-east-s4xcz9z9.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.