HORIZONMarkets
01

Complete project overview

GujRERA · Registration filing
Units
94 units
Mix
94 × Commercial Shed Shop Office
Carpet area
14–241 sq mper-unit range, as filed
Blocks
3
Parking
69 spaces
Land area
6,225 sq m

Timeline

Project startedOct 2015
RERA registeredNov 2017
Proposed completionDec 2018
TodayJul 2026
Construction progress

85% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

94 units across 1 batch
TypeArea sq mCount
Commercial Shed Shop Office6094

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

GLOBAL INFRASTRUCTURE

PARTNERSHIP FIRMPromoter type
Ahmedabad, GujaratBased in
5Projects
5Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
153 homes · 121 plotson the public record across 5 projects
7,173 sq mbuilt-up filed
16,348 sq mplotted area
28,249 sq mland declared
₹12.25 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporationthis project1 of 3 projects
Nagpur Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 3 projects
Parner Nagar PanchayatMunicipal Council1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Ahmedabad City
District
Ahmedabad
Address
SURVEY NO. 191 , GLOBAL BUSINESS PARK, S.P. RING ROAD, ODHAV,
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 2.0km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 155m away
Getting around
Expressway 179 m · Odhav Ring Road FlyoverPrimary road 312 m · Odhav RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 839 m · Odhav LakeCanal 2.5 km · Kharicut Canal
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹12.25 Cr declared to build 94 flats. What that works out to:

₹9.00 Lakh – ₹60.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹13.03 Lakhdeclared cost per flatall-in — land + construction
32%of the cost is land₹577/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Ahmedabad Municipal Corporation

Municipal / Corporation
Building Permitapproved 16 Nov 2017 · 8 yrs ago

The promised possession date (31 Dec 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Ahmedabad Municipal Corporation

Municipal Corporation

Has approved 3,250 RERA projectsabout 1 in 5 in Gujarat, more than any other body in the state.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
2,712
On record
4,25,177 flats · 633 plots
Reach
6 talukas
Since
2007

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.