Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
118 spaces
Land area
1,100 sq m
Sanctioned built-up
5,663 sq m
Recreational open space
14,157 sq m

Timeline

RERA registeredMay 2025
Proposed completionMar 2029
TodayJul 2026
Construction progress
Plinth0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Basement (if any)45%
Excavation56%
Podiums100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

CAVALCADE PROPERTIES PVT LTD

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
12Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
12 projectson the public record across 12 projects
2,21,184 sq mbuilt-up filed
5,46,899 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
MOHAMMADWADI
Taluka
Haveli
District
Pune
Pincode
411060
Survey no.
S. No. 37 H. No. 3+4 (Plot B), S. No. 27 H. No. 1B+2+3 (Plot A) and H. No. 4+5, S. No. 25 H. No. 4 (pt), S. No. 26 H. No. (1+9A) + (2A+2B)
North boundary
30 mtrs wide DP Road
East boundary
24 mtrs wide DP Road
South boundary
Adjacent S No 27 Hissa No 5 pt
West boundary
Amenity Space
What’s nearby
Schools2 schools within 1km · 4 educational institutions within 1km · Library 791m away
HealthcareHospital 606m away · 12 clinics within 1km · Doctor's clinic within 1km
LifestylePark 967m away · 15+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 22m away · Mall 1.0km away · Convenience store within 500m
Getting around
Expressway 2.7 km · Katraj Kondhwa RoadPrimary road 492 m · Kondhwa Main RoadRailway line 3.7 km · Pune - Miraj Railway LineMetro station 4.2km away (Hadapsar)Bus stop within 1km
Legal & regulatory record
Litigation2 cases on record, earliest 2021
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.