HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
24
Buildings
4
Parking
405 spaces
Land area
23,012 sq m
Sanctioned built-up
30,135 sq m
Recreational open space
2,301 sq m

Timeline

RERA registeredJun 2022
Proposed completionDec 2027
TodayJul 2026
Construction progress
Flat fit-out0%
OC-readiness0%
Water Supply0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Fire protection an…10%
Sewerage (Chamber,…15%
Storm Water Drains15%
External finishes25%
Internal finishes35%
Stairs & lifts45%
Internal Roads & F…50%
Podiums80%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

DASSCON REALTY PRIVATE LIMITED

CompanyPromoter type
Pune, MAHARASHTRABased in
4Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
343 homeson the public record across 4 projects
77,358 sq mbuilt-up filed
1,00,534 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Municipal CorporationMunicipal Corporationthis project2 of 3 projects
Pune Municipal Corporation, PuneMunicipal Corporation1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pune (M Corp.)
Taluka
Pune City
District
Pune
Pincode
411048
Survey no.
26/4, NIBM UNDRI ROAD, KONDHWA
North boundary
SR NO 26
East boundary
VILLAGE BOUNDRY SR NO 26
South boundary
SR NO 27
West boundary
SR NO 26 AND 27
What’s nearby
Schools2 schools within 1km · Library 1.5km away
HealthcareHospital 1.1km away · 3 clinics within 1km · Doctor's clinic within 1km
Lifestyle1 park within 500m · 4 restaurants and cafes within 1km
ShoppingSupermarket 1.0km away · Bank 672m away
Getting around
Expressway 2.3 km · Jagannath Shankarsheth MargPrimary road 137 m · Chhatrapati Shivaji Maharaj FlyoverRailway line 3.7 km · Pune - Miraj Railway LineMetro station 3.7km away (Swargate)Limited bus connectivity nearby
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 26/4, NIBM UNDRI ROAD, KONDHWA
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.