HORIZON
Share

LANDMARK

RAJ/P/2023/2649 · RAJ-RERA · https://gethorizon.in/projects/landmark-jaipur-bdotembj

01

Complete project overview

RAJ-RERA · Registration filing
Units
42 units
Mix
6 × 2 BHK (104,204,304,404,504,604) · 6 × 2 BHK (103,203,303,403,503,603) · 6 × 3 BHK (107,207,307,407,507,607) · 5 × 3 BHK (101,201,301,401,501) · 5 × 3 BHK (102,202,302,402,502) · 5 × 3 BHK (105,205,305,405,505)
Carpet area
65–98 sq mper-type range, as filed
Land area
1,196 sq m

Timeline

Construction startJul 2023
RERA registeredAug 2023
Proposed completionDec 2025
TodaySep 2026

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

42 units across 11 batches
BuildingTypeArea sq mCount
LANDMARK3 BHK (101,201,301,401,501)965
LANDMARK3 BHK (102,202,302,402,502)945
LANDMARK3 BHK (105,205,305,405,505)985
LANDMARK3 BHK (106,206,306,406,506)945
LANDMARK3 BHK With Private Terrace (601)961
LANDMARK2 BHK (104,204,304,404,504,604)666
LANDMARK2 BHK (103,203,303,403,503,603)656
LANDMARK3 BHK With Private Terrace (605)981
LANDMARK3 BHK (107,207,307,407,507,607)916
LANDMARK3 BHK With Private Terrace (606)941
LANDMARK3 BHK With Private Terrace (602)941

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Builder registration

SHREE SHYAM ENTERPRISES

OrganisationPromoter type
Jaipur, RajasthanBased in
5Projects
2Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
132 homes · 69 plotson the public record across 5 projects
20,720 sq mbuilt-up filed
4,522 sq mland declared
₹65.19 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SHREE SHYAM ENTERPRISES— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
C-3, C-4, & C-5, KRISHI VIHAR-C, BADARWAS, Jaipur, Jaipur, 302020
Village
BADARWAS
Taluka
Jaipur
District
Jaipur
Pincode
302020
What’s nearby
SchoolsNearest school 1.8km away
HealthcareHospital 710m away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 862 mPrimary road 1.4 kmMetro station 1.6km away (Manasarovar)Bus stop within 1km
Water & environment
Water body 2.5 km · Dravyavati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹12.72 Cr declared to build 42 flats. What that works out to:

₹30.29 Lakhdeclared cost per flatall-in — land + construction
₹2,157/sq ftof built-up area₹23,222/sq m
21%of the cost is land₹2,113/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan IGRS — DLC rates (rural branch)

In Rajasthan it’s called the DLC rate.

₹418per sq yd
₹500per sq m
Which rate
residential, interior plot
Matched to
The rate published for the village of “BHADARWAS”.

What this number is — and isn’t

  • The minimum value Rajasthan’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 7 Aug 2023 · 3 yrs ago

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

421 residential projects still under way within 25 km. Step out ring by ring:

Of the 496 projects the radar draws within 6 km — every kind, every stage — 150 are residential projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

790 m awayGroup Housing

THE SIGNATURE

SHREE ENTERPRISES · Sanganer · Jaipur

Mar 2025registered
Jan 2028target completion
Declared cost₹34.00 CrScale33 flatsAuthorityRAJ-RERA
830 m awayGroup Housing

ALORA

VARDHAMAN ENTERPRISES · Jaipur

Feb 2024registered
Jan 2028target completion
Declared cost₹10.26 CrScale36 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.