Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
21 units across 3 batches
TypeArea sq mCount
1 BHK342
3 BHK871
1 BHK3818
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location
MahaRERA · Registration filing
Village
Andheri
Taluka
Andheri
District
Mumbai Suburban
Pincode
400050
Survey no.
645, 646 and 647
North boundary
Monalisa CHSL
East boundary
Chinchpocali Road
South boundary
Open Ground
West boundary
Existing Structure
What’s nearby
Schools3 schools within 1km · 7 educational institutions within 1km · College or university 597m away
HealthcareHospital 117m away · 15 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 242m away · 113+ restaurants and cafes within 1km
ShoppingSupermarket 276m away · Mall 244m away · Convenience store within 500m
Getting around
Expressway 2.2 kmPrimary road 278 m · Swami Vivekanand RoadRailway line 575 m · Western Railway (Slow)Railway station 598m away (Bandra)20 bus stops within 500m
Water & environment
Water body 362 m · Bandra Talao
distances only — not a flood assessment
Location — done
04
Government Guidance Rate
Maharashtra registration department
In Maharashtra it’s called the ready reckoner rate.
No government guidance rate is shown for this project.
Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Complaints & litigation
MahaRERA · public record
Complaints before MahaRERA
MahaRERA's own register
4 complaints
MahaRERA's list gives each complaint's number and date, not its status or outcome — and only disputes escalated to MahaRERA appear here at all.
Number
Date
CC12602702
9 May 2026
CC12602700
9 May 2026
CC12602696
9 May 2026
CC12602697
9 May 2026
What the builder declared
Declared to MahaRERA
Litigation
None declared to MahaRERA
The builder's own declaration at registration — not a court's or MahaRERA's finding. A flagged line is worth checking with MahaRERA.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with MahaRERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
3,475 residential projects still under way within 25 km. Step out ring by ring:
Of the 1,897 projects the radar draws within 6 km — every kind, every stage — 696 are residential projects still under way. This list keeps only those, and looks further out.
36 projects within 1 km — showing the nearest 6.
220 m awayMixed
Shikhar Garden
Shikhar Realty · Chawane · Panvel
3 yr 9 mo
Mar 2026registered
Dec 2029target completion
Government Guidance Rate₹27,258/sq ydScale178 flatsAuthorityMahaRERA