Complete project overview

MahaRERA · Registration filing
Floors
33
Buildings
2
Parking
92 spaces
Land area
1,926 sq m
Sanctioned built-up
6,845 sq m
Recreational open space
1,672 sq m

Timeline

RERA registeredJul 2020
Proposed completionSep 2026
TodayJul 2026
Construction progress
Water Supply0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Energy managemcnt0%
Electrical meter r…0%
OC-readiness11%
Storm Water Drains25%
Fire protection an…25%
Flat fit-out26%
External finishes26%
Internal finishes30%
Aggregate area of …40%
Water conservation…60%
Stairs & lifts69%
Community Building…70%
Treatment And Disp…70%
Sewerage (Chamber,…80%
Superstructure90%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

VIKRAM DEVELOPERS AND PROMOTERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
4Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
4 projectson the public record across 4 projects
41,988 sq mbuilt-up filed
9,476 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimpri Chinchawad (M Corp.)
Taluka
Haveli
District
Pune
Pincode
411027
Survey no.
SURVEY NO 14 PART , 15 PART AND 16 PART PIMPLE NILAKH
North boundary
BY CTS NO 864 PART AND CTS NO 762 PART
East boundary
CTS NO 762 PART AND PROPOSED WING F
South boundary
BY CTS NO 804
West boundary
BY MIDORI TOWER PHASE 2 WING D
What’s nearby
Schools1 school within 1km · Library 1.7km away · Kindergarten within 500m
HealthcareHospital 865m away · 2 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 869m away · 3 restaurants and cafes within 1km
ShoppingSupermarket 920m away · Mall 1.1km away · Bank 329m away
Getting around
Expressway 2.3 km · Katraj - Dehu Road BypassPrimary road 1.0 km · Wakad RoadRailway line 4.9 km · Mumbai–Pune RailwayMetro station 1.4km away (High Street)Bus stop within 500m
Water & environment
River 542 m · Mula
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO 14 PART , 15 PART AND 16 PART PIMPLE NILAKH
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.