My Moon Residency

RAJ/P/2018/759 · RAJ-RERA · https://gethorizon.in/projects/my-moon-residency-jaipur-xjx055zb

01

Complete project overview

RAJ-RERA · Registration filing
Project name
My Moon Residency
Land area
753 sq m
Completion deadline extended
1 extension on record — latest to 31 May 2021declared reason: force majeure
Description
The Total Cost of project is Rs. 40378021 in which Land Cost - Rs. 5378021 and Development Cost - Rs. 35000000

Timeline

RERA registeredJun 2018
Proposed completionMay 2020
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

MY MOON BUILDCON

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2018–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RAJ-RERA · Registration filing
Address
144, Jhotwara, Jaipur, Salyawas, Jaipur, Jaipur, 302012
Village
Salyawas
Taluka
Jaipur
District
Jaipur
Pincode
302012
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.7km away · Library 1.7km away
HealthcareHospital 322m away · 3 clinics within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 282m away · Mall 1.4km away · Bank 837m away
Getting around
Expressway 1.8 km · FlyoverPrimary road 2.2 km · Kalwad RoadRailway line 1.3 kmRailway station 3.0km away (Dahar-Ka-Balaji)2 bus stops within 500m
04

Government Guidance Rate

Rajasthan IGRS — DLC rates

In Rajasthan it’s called the DLC rate.

₹10,619per sq yd
₹12,700per sq m
Which rate
residential, interior plot
Matched to
The rate published for “Salyawas Village”.
Highest rate
₹13,712 per sq yd — the top road-facing rate among the residential rates published for this colony

By the road it faces

interior plot₹12,700 / sq m₹10,619 / sq yd
road-facing₹16,400 / sq m₹13,712 / sq yd
41–60 ft road₹18,040 / sq m₹15,084 / sq yd

The same land, priced by the width of the road it faces — each band the middle of the residential rates published for this colony.

What this number is — and isn’t

  • The minimum value Rajasthan’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of colony, and says so above. How Horizon decides what to show.
05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 13 Jun 2018 · 8 yrs ago

The promised possession date (31 May 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

418 residential projects still under way within 25 km. Step out ring by ring:

Of the 376 projects the radar draws within 6 km — every kind, every stage — 130 are residential projects still under way. This list keeps only those, and looks further out.

6 projects within 1 km — showing the nearest 6.

560 m awayGroup Housing

BALAJI AASHIYANA I

BALAJI BUILDERS · Jaipur

Apr 2025registered
Nov 2027target completion
Declared cost₹2.52 CrScale36 flatsAuthorityRAJ-RERA
560 m awayGroup Housing

BALAJI AASHIYANA II

BALAJI BUILDERS · Jaipur

Apr 2025registered
Nov 2027target completion
Declared cost₹8.44 CrScale30 flatsAuthorityRAJ-RERA
560 m awayGroup Housing

The Royal Green I

BALAJI CONSTRUCTION · Jaipur

Aug 2025registered
Jun 2028target completion
Declared cost₹21.70 CrScale70 flatsAuthorityRAJ-RERA
560 m awayGroup Housing

THE ROYAL GREEN II

SHYAM BUILDERS AND DEVELOPERS · Jaipur

Sep 2025registered
Jun 2028target completion
Declared cost₹19.71 CrScale60 flatsAuthorityRAJ-RERA
610 m awayGroup Housing

RAMAA PRIME-1ST

KRISHNAA BALRAM RESIDENCY PRIVATE LIMITED · Jaipur

Mar 2021registered
May 2026target completion
Declared cost₹27.50 CrScale27 flatsAuthorityRAJ-RERA
610 m awayGroup Housing

SKY PALACIO

AJAY KUMAR ARYA · Jaipur

Mar 2024registered
Jan 2027target completion
Declared cost₹15.00 CrScale40 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.