HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
15 units
Unit mix
15 × 2BHK
Saleable area
88–101 sq mper unit, as filed
Floors
5
Land area
524 sq m
Built-up area
1,144 sq m

Timeline

RERA approvedFeb 2018
Proposed completionFeb 2024
TodayJul 2026
Construction progress

29% overall, as filed

Basement & plinth0%
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal finishes40%
Stilt floor60%
Excavation90%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

15 of 15 available
BuildingFloorTypeArea sq mAvailable
S K DREAMS BLOCK A12BHK1011 of 1
S K DREAMS BLOCK A12BHKmortgaged881 of 1
S K DREAMS BLOCK A12BHKmortgaged981 of 1
S K DREAMS BLOCK A22BHK1011 of 1
S K DREAMS BLOCK A22BHK881 of 1
S K DREAMS BLOCK A22BHK981 of 1
S K DREAMS BLOCK A32BHK1011 of 1
S K DREAMS BLOCK A32BHK881 of 1
S K DREAMS BLOCK A32BHK981 of 1
S K DREAMS BLOCK A42BHK1011 of 1
S K DREAMS BLOCK A42BHK881 of 1
S K DREAMS BLOCK A42BHK981 of 1
S K DREAMS BLOCK A52BHK1011 of 1
S K DREAMS BLOCK A52BHK881 of 1
S K DREAMS BLOCK A52BHK981 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

S K CONSTRUCTIONS AND DEVELOPERS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
4Projects
2Cities
2018–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
75 homeson the public record across 4 projects
7,417 sq mbuilt-up filed
3,238 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
RAMACHANDRA PURAM
Mandal
RC PURAM
District
Sangareddy
Pincode
500050
North boundary
NEIGHBOURS HOUS
East boundary
PLOT NO 3 PART
South boundary
ROAD
West boundary
ROAD
What’s nearby
Schools1 school within 1km
HealthcareHospital 1.3km away · 4 clinics within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.3km away
ShoppingSupermarket 935m away · Bank 383m away
Getting around
Expressway 345 mPrimary road 3.6 kmRailway line 624 mRailway station 1.0km away (Ramachandrapuram TS)Bus stop within 500m
Water & environment
Water body 1.1 km · Ramachandrapuram Cheruvu
distances only — not a flood assessment
Declared external development
Water supply20%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 381/AA AND 382/AA

The promised possession date (10 Feb 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.