Complete project overview

GujRERA · Registration filing
Units
64 units
Mix
48 × Residential · 16 × Commercial
Carpet area
28–166 sq mper-unit range, as filed
Parking
16 spaces
Land area
3,217 sq m

Timeline

Project startedJan 2021
RERA registeredOct 2021
Proposed completionDec 2024
TodayJul 2026
Construction progress

100% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

64 units across 2 batches
TypeArea sq mCount
Residential14348
Commercial5916

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

MARUTI BUILDCON

PARTNERSHIP FIRMPromoter type
Gandhinagar, GujaratBased in
14Projects
10Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,599 homeson the public record across 14 projects
1,12,213 sq mbuilt-up filed
41,699 sq mland declared
₹168.82 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation3 of 13 projects
Others3 of 13 projects
Ahmedabad Urban Development AuthorityUrban Development Authoritythis project2 of 13 projects
Gandhinagar Urban Development AuthorityUrban Development Authority1 of 13 projects
Kadi MunicipalityMunicipal / Corporation1 of 13 projects
Kulgaon Badlapur Municipal CouncilMunicipal Council1 of 13 projects
Nashik Municipal CorporationMunicipal Corporation1 of 13 projects
Surat Municipal CorporationMunicipal / Corporation1 of 13 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Gandhinagar
District
Gandhinagar
Address
Siddhivinayak Signature, Beside Koteshwar Gurukul Sankul,Opp. Shikhar 49, Koteshwar, Gandhinagar
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.3km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 1.9km away
Getting around
Expressway 2.2 km · Sardar Patel Ring RoadPrimary road 1.6 kmRailway line 2.8 kmMetro station 1.3km away (Koteshwar Road)Limited bus connectivity nearby
Water & environment
Water body 571 mRiver 935 m · Sabarmati River
distances only — not a flood assessment
Land, title & encumbrance
MortgageLoan outstanding · ₹4.81 Cr outstanding
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹26.72 Cr declared to build 64 flats. What that works out to:

₹11.50 Lakh – ₹80.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹41.75 Lakhdeclared cost per flatall-in — land + construction
₹3,186/sq ftof carpet area₹34,297/sq m
10%of the cost is land₹772/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Ahmedabad Urban Development Authority

Urban Development Authority
Building Permitapproved 6 Oct 2021 · 4 yrs ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Building-Use (BU) permission — the occupancy sign-off, on record

All 1 block carry a Building-Use (BU) permission (latest 9 Aug 2024)— Gujarat’s legal-to-occupy sign-off, and the completion proof most RERA records simply don’t carry. Still confirm the BU covers your specific unit before you rely on it.

The approving body, at scale

Ahmedabad Urban Development Authority

Urban Development Authority

Has approved 2,400 RERA projectsabout 1 in 7 in Gujarat.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,936
On record
3,12,468 flats · 1,153 plots
Reach
22 talukas
Since
2007

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.