Complete project overview

RAJ-RERA · Registration filing
Units
467 units
Mix
256 × RESIDENTIAL & COMMERCIAL · 48 × Flat No. C-103 to C-1203, C-104 to C-1204, C-105 to C-1205, C-107 to C-1207 · 36 × Flat No. C-101 to C-1201, C-102 to C-1202, C-106 to C-1206 · 24 × Flat No. B-103 to B-1203, B-104 to B-1204 · 24 × Flat No. C-110 to C-1210, C-111 to C-1211 · 20 × Flat No. C-308 to C-1208, C-309 to C-1209
Carpet area
30–12079 sq mper-type range, as filed
Land area
6,499 sq m
Completion deadline extended
3 extensions on record — latest to 21 Jun 2024declared reason: force majeure
Description
1. We have got the approval of construction of the said project "Skypark" from UIT, Kota as per letter No. F-7/DTP/2017/66-78 dated 13/01/2017 till B+8th floor as on date, as soon as the approval of upper floors has been granted by the concerned authority, we will submit the copy of the same and as Fire NOC has been expired as on date of the aforesaid project, we will also submit the copy of the same along with the third phase permission letter.By mistake we have applied the project "Skypark" under mix use, but our commercial FAR is below 3% as per by laws and UIT approvals. So we request you to kindly consider the project under group housing. We bring into your kind notice that we have applied for registration of our project “Skypark” situated at Commercial Scheme, Subhash Nagar, Kota (Raj) vide Application No. RAJ-RERA-APP-P-2017-656 dated 29/07/2017. The said plot has been allotted to our company by UIT, Kota through open auction and get allotment in the name of our company vide their office letter No. F-3/Auction/2015/1792 dated 09/03/2015 in which it is clearly mentioned that the allotted land address is Plot No. Commercial Scheme, Subhash Nagar, Kota and there is no such plot number of the aforesaid land. 2. The project has been extended for the period of 1 year and before updation the estimated finish date of the project is 15-03-2020. Also, maps of 9th to 12th floor updated with subsequent changes on 05-06-2020 along with the extension. This bears the approval of the Honorable Chairman.

Timeline

Construction startFeb 2016
RERA registeredOct 2017
Proposed completionMar 2021
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

467 units across 34 batches
BuildingTypeArea sq mCount
SKYPARKFlat No. C-103 to C-1203, C-104 to C-1204, C-105 to C-1205, C-107 to C-12077948
SKYPARKFlat No. A-105 to A-120510412
SKYPARKFlat No. B-103 to B-1203, B-104 to B-120410924
SKYPARKFlat No. B-101 to B-120114712
SKYPARKFlat No. B-102 to B-120210512
SKYPARKFlat No. C-308 to C-1208, C-309 to C-12097920
SKYPARKFlat No. C-101 to C-1201, C-102 to C-1202, C-106 to C-12069436
SKYPARKFlat No. C-110 to C-1210, C-111 to C-12118124
SKYPARKFlat No. A-1301 (PH)1441
SKYPARKFlat No. A-1303 (PH)1151
SKYPARKFlat No. B-1301 (PH)1471
SKYPARKFlat No. B-1302 (PH)1271
SKYPARKFlat No. C-109 (1 BHK)411
SKYPARKFlat No. C-1301 (PH)1071
SKYPARKFlat No. C-1302 (PH)911
SKYPARKFlat No. C-1303 (PH)771
SKYPARKFlat No. C-1304 (PH)911
SKYPARKFlat No. C-1305 (PH)911
SKYPARKRESIDENTIAL & COMMERCIAL12,079134
SKYPARKRESIDENTIAL & COMMERCIAL4,91167
SKYPARKRESIDENTIAL & COMMERCIAL5,85555
SKYPARKShop No. S1811
SKYPARKShop No. S10391
SKYPARKShop No. S11451
SKYPARKShop No. S12391
SKYPARKShop No. S13641
SKYPARKShop No. S-2331
SKYPARKShop No. S3411
SKYPARKShop No. S4601
SKYPARKShop No. S5431
SKYPARKShop No. S6571
SKYPARKShop No. S7301
SKYPARKShop No. S8301
SKYPARKShop No. S9331

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

SUNPRIME INFRATECH PVT LTD

OrganisationPromoter type
Kota, RajasthanBased in
1Projects
1City
2017–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
COMMERCIAL SCHEME, SUBHASH NAGAR, KOTA, Ladpura, Kota, 324005
Village
KOTA
Taluka
Ladpura
District
Kota
Pincode
324005
What’s nearby
Schools2 schools within 1km · 4 educational institutions within 1km · College or university 991m away
HealthcareHospital 258m away · 5 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km · Playground within 500m · 9 restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Mall 1.6km away · Convenience store within 500m
Getting around
Expressway 3.1 km · Kota BypassPrimary road 541 mRailway line 1.9 km · Mumbai - Delhi RailwayRailway station 2.5km away (Dakaniya Talav)Limited bus connectivity nearby
Water & environment
Water body 401 mRiver 507 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹103.92 Cr declared to build 467 flats. What that works out to:

₹22.25 Lakhdeclared cost per flatall-in — land + construction
₹2,442/sq ftof built-up area₹26,286/sq m
18%of the cost is land₹2,722/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 27 Oct 2017 · 8 yrs ago

The promised possession date (15 Mar 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.