01

Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
110 sq mper unit, as filed
Floors
5
Land area
712 sq m
Built-up area
1,798 sq m

Timeline

RERA approvedJun 2018
Proposed completionJun 2024
TodaySep 2026
Construction progress

46.5% overall, as filed

Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal finishes30%
Stairs & lifts60%
Superstructure75%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
BALAJI NILAYAM12BHK1104 of 4
BALAJI NILAYAM22BHKmortgaged1104 of 4
BALAJI NILAYAM32BHK1104 of 4
BALAJI NILAYAM42BHK1104 of 4
BALAJI NILAYAM52BHK1104 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the builder that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Builder registration

SRI VENKATESHWARA BUILDERS AND DEVELOPERS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
5Projects
1City
2018–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
104 homeson the public record across 5 projects
9,621 sq mbuilt-up filed
3,468 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SRI VENKATESHWARA BUILDERS AND DEVELOPERS— the full portfolio →

03

Location

RERA Telangana · Registration filing
Locality
BLOCK NO 7
Village
HAYATHNAGAR
Mandal
Hayathnagar
District
Ranga Reddy
Pincode
501505
North boundary
ROAD
East boundary
ROAD
South boundary
NEIGHBOURS PLOTS
West boundary
ROAD
What’s nearby
Schools1 school within 500m
HealthcareHospital 589m away · 1 clinic within 1km
LifestylePark 2.0km away · Gym or sports centre 1.3km away
ShoppingSupermarket 219m away · Bank 546m away · ATM within 500m
Getting around
Expressway 72 m · Vijaywada HighwayPrimary road 3.5 km · Hyderabad - Nagarjuna Sagar RoadNo metro or railway within 5kmBus stop within 500m
Water & environment
Water body 746 m · Kummari Kunta
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Government Guidance Rate

Telangana Registration & Stamps

In Telangana it’s called the market value — the registration department's figure, not a sale price.

₹17,900per sq yd
₹21,408per sq m
₹3,000per sq ft for a flat · same schedule
Which rate
residential (urban)
Matched to
The middle village rate across 6 villages of “HAYATHNAGAR” mandal — the mandal, not this village.
In force
effective May 2026

What this number is — and isn’t

  • The minimum value Telangana’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of mandal, and says so above. How Horizon decides what to show.
05

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 260 PART

The promised possession date (30 Jun 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Telangana

07

Other projects nearby

The register · within 25 km

1,394 residential projects still under way within 25 km. Step out ring by ring:

Of the 451 projects the radar draws within 6 km — every kind, every stage — 199 are residential projects still under way. This list keeps only those, and looks further out.

17 projects within 1 km — showing the nearest 6.

250 m awayResidential

OM SRI SHIVA SAI RESIDENCY

S M INFRATECH CONSTRUCTIONS · BAGH HAYATHNAGAR VILLAGE · Hayathnagar

Aug 2025registered
Aug 2028target completion
Government Guidance Rate₹17,900/sq ydScale10 flatsAuthorityRERA Telangana
400 m awayResidential

PRIDE ELINA

PRIDE INFRA DEVELOPERS · WARD NO 4 · Hayathnagar

Mar 2021registered
Mar 2027target completion
Government Guidance Rate₹17,900/sq ydScale10 flatsAuthorityRERA Telangana
420 m awayResidential

RAINBOW SAI PADMAVATHI RESIDENCY

rainbow constructions · HAYATH NAGAR

Oct 2019registered
Oct 2026target completion
Scale10 flatsAuthorityRERA Telangana
600 m awayResidential

YJR PRIDE

AR DREAM HOMES · Kalvancha Revenue Village · Hayathnagar

Nov 2025registered
Nov 2028target completion
Government Guidance Rate₹21,400/sq ydScale25 flatsAuthorityRERA Telangana
650 m awayResidential

VEDA s BREEZE BLOWS

VEDA HOMES · HAYATHNAGAR

Feb 2021registered
Feb 2027target completion
Scale20 flatsAuthorityRERA Telangana
650 m awayResidential

SIRI KUBERA PARK VIEW

KUBERA DEVELOPERS · HAYATHNAGAR · Hayathnagar

Nov 2023registered
Nov 2026target completion
Government Guidance Rate₹17,900/sq ydScale10 flatsAuthorityRERA Telangana

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.