HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
30 units
Mix
17 × 3BHK · 13 × 2BHK
Booked
30 of 30 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,013 sq m
Floor area
4,158 sq m
Description
VARMA SPECTRUM

Timeline

Project startedJan 2019
RERA registeredJun 2021
Proposed completionAug 2023
TodayJul 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 30 available
TypeArea sq mAvailable
3BHK840 of 4
2BHK570 of 2
3BHK1110 of 1
2BHK590 of 11
3BHK840 of 12

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

VARMA HOMES PRIVATE LIMITED

CompanyPromoter type
Thrissur, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
27Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,337 homeson the public record across 27 projects
2,13,358 sq mbuilt-up filed
56,171 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Cochin Municipal CorporationMunicipal Corporation3 of 27 projects
Kochi Municipal CorporationMunicipal Corporation3 of 27 projects
Thrissur Municipal CorporationMunicipal Corporation3 of 27 projects
Thiruvananthapuram Municipal CorporationMunicipal Corporation2 of 27 projects
Tripunithura MuncipalityLocal body (LSGI)2 of 27 projects
Tripunithura MunicipalityMunicipality2 of 27 projects
Cheranallur Grama Panchayath ErnakulamLocal body (LSGI)1 of 27 projects
Chottanikkara GramapanchayatLocal body (LSGI)1 of 27 projects
Kadinamkulam Grama PanchayatGrama Panchayat1 of 27 projects
Maradu MunicipalityMunicipality1 of 27 projects
Nadathara GramapanchayatLocal body (LSGI)this project1 of 27 projects
Nedumbassery Grama Panchayat ErnakulamLocal body (LSGI)1 of 27 projects
Thirumala VillageLocal body (LSGI)1 of 27 projects
Thrikkakara MunicipalityMunicipality1 of 27 projects
Thripunithura MuncipalityLocal body (LSGI)1 of 27 projects
Thripunithuta MuncipalityLocal body (LSGI)1 of 27 projects
Thrivananthapuram Muncipal Municipal CorporationMunicipal Corporation1 of 27 projects
Tripunithura Municipality ErnakulamLocal body (LSGI)1 of 27 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Moorkanikkara Road
Village
NADATHARA
Taluk
Thrissur
District
Thrissur
Pincode
680751
Survey no.
Sy.No.184/1, Re Sy.No.141
Patta no.
3981
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km · College or university 1.3km away
HealthcareHospital 1.4km away · Clinic within 2km
LifestylePark 1.6km away
ShoppingNo supermarket within 2km · Mall 528m away · Bank 641m away
Getting around
Expressway 1.4 km · Salem - Kochi - Kanyakumari HighwayPrimary road 2.8 km · Thrissur - Mannuthy RoadNo metro or railway within 5km5 bus stops within 500m
Water & environment
Water body 152 m · Polukkayal Vaka KulamCanal 355 mRiver 743 m · Manali River
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Nadathara Gramapanchayat

Local body (LSGI)
approved 12 Dec 2017 · 8 yrs ago
Building Permit no. A7-2123/17Survey no. Sy.No.184/1, Re Sy.No.141

The promised possession date (31 Aug 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A7-2123/17 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.