HORIZON
Share

VEDA

PR1180002601666 · MahaRERA · https://gethorizon.in/projects/veda-akurli-borivali-u1lma2lb

01

Complete project overview

MahaRERA · Registration filing
Project name
VEDA
Land area
1,014 sq m

Timeline

RERA registeredAug 2026
Proposed completionDec 2031
TodaySep 2026
Construction progress
Excavation0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

VESTICO REALTY LLP

Limited Liability PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Akurli
Taluka
Borivali
District
Mumbai Suburban
Pincode
400101
Survey no.
CTS NO.171/48/10
North boundary
BY ADJ. CLUSTER PLOT NO.3
East boundary
BY ADJ H.I.G. PLOT NO.2(PT) & 3(PT)
South boundary
BY ADJ 9.00M WIDE RD
West boundary
BY ADJ. CLUSTER PLOT NO.5
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 75m away · Clinic within 2km
Lifestyle1 park within 500m · Playground within 500m · Gym or sports centre 1.9km away
ShoppingSupermarket 1.4km away · Mall 1.7km away
Getting around
Expressway 1.3 kmPrimary road 2.6 km · Swami Vivekanand RoadRailway line 2.3 kmMetro station 1.4km away (Poisar)Limited bus connectivity nearby
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. CTS NO.171/48/10
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

4,184 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,060 projects the radar draws within 6 km — every kind, every stage — 694 are residential projects still under way. This list keeps only those, and looks further out.

16 projects within 1 km — showing the nearest 6.

80 m awayResidential / Group Housing

AVASA

KOLTER REALTY LLP · Akurli · Borivali

Aug 2026registered
Dec 2031target completion
AuthorityMahaRERA
320 m awayResidential / Group Housing

RIVIERA

Meghna Aakar Constructions · Pahadi-Goregaon · Borivali

Dec 2024registered
Mar 2027target completion
Government Guidance Rate₹1,47,593/sq ydScale35 flatsAuthorityMahaRERA
430 m awayOthers

SHETH SQUARE

SHETH BUILDERS PRIVATE LIMITED · Pahadi-Goregaon · Borivali

Jul 2024registered
May 2029target completion
Government Guidance Rate₹1,35,001/sq ydScale68 flatsAuthorityMahaRERA
470 m awayOthers

Solitaire Edge

MAHAVEER CONSTRUCTION · Borivali

Sep 2021registered
Dec 2026target completion
Scale127 flatsAuthorityMahaRERA
500 m awayResidential / Group Housing

Mahindra Vista Phase 1

Mahindra Lifespace Developers limited · Akurli · Borivali

Feb 2024registered
Dec 2029target completion
Government Guidance Rate₹1,20,728/sq ydScale601 flatsAuthorityMahaRERA
560 m awayResidential / Group Housing

PATON TOWERS

PRAVIN VIRAM SATRA · Akurli · Borivali

Feb 2020registered
Dec 2026target completion
Scale531 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.