Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
258 spaces
Land area
2,162 sq m
Sanctioned built-up
8,786 sq m

Timeline

RERA registeredNov 2022
Proposed completionDec 2026
TodayJul 2026
Construction progress
Flat fit-out0%
External finishes0%
OC-readiness0%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Solid Waste Manage…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

AMBAR ICON LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
LOHGAON
Taluka
Haveli
District
Pune
Pincode
411014
Survey no.
153/1, 153/2, 153/3, 153/4 AND 153/7(P)
North boundary
CTS 179
East boundary
CTS NO 25 PLOT NO 95
South boundary
18 MTR DP ROAD
West boundary
CTS 153 3 154 PLOT NO 97
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · College or university 567m away
HealthcareHospital 145m away · 6 clinics within 1km · Pharmacy within 1km
LifestylePark 1.8km away · 13+ restaurants and cafes within 1km
ShoppingSupermarket 628m away · Convenience store within 1km · Bank 175m away
Getting around
Expressway 638 m · Nagar RoadPrimary road 1.6 km · National Games MargRailway line 4.1 kmRailway station 637m away (Ramwadi Station)Bus stop within 1kmAirport 2.3km away
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation Building Control Department

Municipal Corporation
Building Permit
Survey no. 153/1, 153/2, 153/3, 153/4 AND 153/7(P)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.