01

Complete project overview

MahaRERA · Registration filing
Units
94 units
Floors
11
Buildings
2
Parking
34 spaces
Land area
7,408 sq m
Sanctioned built-up
6,266 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2024
TodaySep 2026
Construction progress
Flat fit-out0%
Stairs & lifts0%
Water Supply0%
Storm Water Drains0%
Street Lighting0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
OC-readiness5%
Sewerage (Chamber,…20%
Internal finishes30%
External finishes30%
Internal Roads & F…60%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

PLATINUM REALTY AND INFRASTRUCTURE PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2017–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhiwandi (M Corp.)
Taluka
Bhiwandi
District
Thane
Pincode
421302
Survey no.
S. NO. 1641P, 1642P, 1643
North boundary
164-2P
East boundary
164-2 NKT SCHOOL
South boundary
164-4
West boundary
NARPOLI VILLAGE
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 369m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 285m away
Getting around
Expressway 12 m · Agra RoadPrimary road 943 mRailway line 1.4 kmRailway station 1.4km away (Bhivandi Road)2 bus stops within 500m
Water & environment
Water body 1.0 kmRiver 2.3 km · Kamvadi
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹24,415per sq yd
₹29,200per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 71 divisions of “Bhiwandi (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹23,495₹57,191 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Bhivandi Nijamsur Saher Mahanagrpalika Bhivandi Ji Thane

Building Permit
Survey no. S. NO. 1641P, 1642P, 1643

The promised possession date (30 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

3,564 residential projects still under way within 25 km. Step out ring by ring:

Of the 408 projects the radar draws within 6 km — every kind, every stage — 139 are residential projects still under way. This list keeps only those, and looks further out.

12 projects within 1 km — showing the nearest 6.

10 m awayResidential / Group Housing

ROSE RESIDENCY

KUNAL RAMESH KARANIYA · Bhiwandi

Jun 2022registered
Sep 2026target completion
Government Guidance Rate₹24,415/sq ydScale78 flatsAuthorityMahaRERA
290 m awayResidential / Group Housing

SHATRUNJAY HEIGHTS

ONYX BUILDCON LLP · Bhiwandi

Sep 2021registered
Mar 2026target completion
Government Guidance Rate₹24,415/sq ydScale204 flatsAuthorityMahaRERA
300 m awayMixed

Swami Enclave

M/s. Om Sai Ram Infra · Vada

Oct 2025registered
Oct 2028target completion
Government Guidance Rate₹26,840/sq ydScale30 flatsAuthorityMahaRERA
320 m awayResidential / Group Housing

DHEERAJ HEIGHTS- PHASE-II

SASHWAT HOME · Bhiwandi

Jun 2023registered
Dec 2026target completion
Government Guidance Rate₹24,415/sq ydScale110 flatsAuthorityMahaRERA
370 m awayMixed

CLASSIC PLAZA

NEW CLASSIC CONSTRUCTION · Bhiwandi

Jul 2025registered
Dec 2028target completion
Government Guidance Rate₹24,415/sq ydScale70 flatsAuthorityMahaRERA
490 m awayMixed

LEO BUSINESS COMPLEX

LEO INFRA AND DEVELOPER · Bhiwandi

Jul 2025registered
Dec 2027target completion
Government Guidance Rate₹24,415/sq ydScale67 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.