Omkar Residency A-Wing

P51700046189 · MahaRERA · https://gethorizon.in/projects/omkar-residency-a-wing-bhiwandi-m-corp-vdi3tzwh

01

Complete project overview

MahaRERA · Registration filing
Project name
Omkar Residency A-Wing
Units
36 units
Floors
9
Buildings
2
Land area
1,923 sq m
Sanctioned built-up
1,975 sq m

Timeline

RERA registeredJun 2022
Proposed completionDec 2025
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Electrical meter r…0%
Internal finishes85%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

K K GROUP

PartnershipPromoter type
Thane, MAHARASHTRABased in
3Projects
2Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
36 homes · 292 plotson the public record across 3 projects
1,975 sq mbuilt-up filed
67,226 sq mplotted area
69,149 sq mland declared
₹21.84 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Mathura-Vrindavan Development AuthorityDevelopment Authority2 of 3 projects
Otherthis project1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from K K GROUP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Bhiwandi (M Corp.)
Taluka
Bhiwandi
District
Thane
Pincode
421302
Survey no.
S.No 2/5/B
North boundary
As Per Government Record
East boundary
As Per Government Record
South boundary
As Per Government Record
West boundary
As Per Government Record
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.0 km · Agra RoadPrimary road 1.0 kmRailway line 367 mRailway station 416m away (Bhivandi Road)Limited bus connectivity nearby
Water & environment
Water body 1.1 kmRiver 4.1 km · Kamvadi
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹24,415per sq yd
₹29,200per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 71 divisions of “Bhiwandi (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹23,495₹57,191 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Other

Building Permit
Survey no. S.No 2/5/B

The promised possession date (13 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Other

Planning authority

Has approved 12 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
12
On record
340 flats · 0 plots
Reach
6 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

3,723 residential projects still under way within 25 km. Step out ring by ring:

Of the 488 projects the radar draws within 6 km — every kind, every stage — 163 are residential projects still under way. This list keeps only those, and looks further out.

3 projects within 1 km — showing the nearest 3.

690 m awayResidential / Group Housing

Everest Heights

OMNIBUILD REALTY LLP · Bhiwandi

Jul 2026registered
Dec 2032target completion
Government Guidance Rate₹24,415/sq ydScale56 flatsAuthorityMahaRERA
760 m awayResidential / Group Housing

SUMERU HILLS

TESCO REALTY LLP · Bhiwandi

Jun 2024registered
Dec 2029target completion
Government Guidance Rate₹24,415/sq ydScale87 flatsAuthorityMahaRERA
870 m awayMixed

Atlanta Luxuria

SRI BALAJI DEVELOPER · Bhiwandi

Dec 2025registered
Dec 2030target completion
Government Guidance Rate₹24,415/sq ydScale76 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.