HORIZON
Share

CHARKOP GITANJALI CO OP HOUSING SOCIETY LIMITED

P51800045647 · MahaRERA · https://gethorizon.in/projects/charkop-gitanjali-co-op-housing-society-borivali-djcijg75

Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
53 units
Floors
26
Buildings
2
Parking
53 spaces
Land area
788 sq m
Sanctioned built-up
3,740 sq m

Timeline

RERA registeredMay 2022
Proposed completionMay 2025
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

CHARKOP GITANJALI CO-OP HOUSING SOCIETY LIMITED

SocietyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2022–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Borivali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400067
Survey no.
CTS 1C-2/230 SURVEY 149 PLOT NO 130
North boundary
PLOT NO 128 ADJ CTS 1C-2-213
East boundary
RSC 11 14 MTR WIDE ROAD
South boundary
PLOT NO 132 ADJ CTS 1C-2-235
West boundary
30 SQM CTS 1C-2-212 ADJ 1C-2-231 ADJ 1C-2-234
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 139m away · 4 clinics within 1km · Pharmacy within 1km
LifestylePark 811m away · Gym or sports centre 1.7km away · 4 restaurants and cafes within 1km
ShoppingSupermarket 818m away · Mall 650m away · Bank 418m away
Getting around
Expressway 4.1 km · Western Express HighwayPrimary road 1.2 km · Goregaon Link RoadRailway line 3.1 km · Western Railway Virar to BorivaliMetro station 1.3km away (Dahanukarwadi)4 bus stops within 500m
Water & environment
Water body 788 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. CTS 1C-2/230 SURVEY 149 PLOT NO 130

The promised possession date (31 May 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,735 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,963 projects the radar draws within 6 km — every kind, every stage — 680 are residential projects still under way. This list keeps only those, and looks further out.

22 projects within 1 km — showing the nearest 6.

200 m awayOthers

ORION HEIGHTS

CHARKOP ORION CO-OPERATIVE HOUSING SOCIETY LIMITED · Borivali

Apr 2022registered
Mar 2027target completion
Government Guidance Rate₹1,23,889/sq ydScale143 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

RAJ ONE

RAJ REALTORS · Charkop · Borivali

Mar 2024registered
Aug 2027target completion
Scale170 flatsAuthorityMahaRERA
280 m awayResidential / Group Housing

Navrang Navdeep

OXFORD DOWNTOWN REALTY LLP · Charkop · Borivali

Aug 2026registered
Dec 2029target completion
Government Guidance Rate₹1,27,493/sq ydAuthorityMahaRERA
300 m awayResidential / Group Housing

Sai Divine

SHREEJI DEVELOPERS · Charkop · Borivali

May 2023registered
Dec 2026target completion
Scale91 flatsAuthorityMahaRERA
300 m awayResidential / Group Housing

CHARKOP DR AMBEDKAR COLLEGE TEACHERS CO OPERATIVE HOUSING SOCIETY LTD

CHARKOP DR AMBEDKAR COLLEGE TEACHERS CO-OPERATIVE HOUSING SOCIETY LTD · Kandivali · Borivali

Nov 2023registered
Dec 2026target completion
Scale61 flatsAuthorityMahaRERA
390 m awayResidential / Group Housing

DEM ICON

DEM Developers LLP · Kandivali · Borivali

Apr 2023registered
Mar 2026target completion
Government Guidance Rate₹1,23,889/sq ydScale106 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.