Complete project overview

MahaRERA · Registration filing
Floors
15
Buildings
3
Parking
136 spaces
Land area
2,310 sq m
Recreational open space
208 sq m

Timeline

RERA registeredMay 2024
Proposed completionDec 2027
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Fire protection an…0%
Open Parking0%
Internal finishes45%
Superstructure56%
Stairs & lifts56%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SAGAROM DB INFRA LLP

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Charkop
Taluka
Borivali
District
Mumbai Suburban
Pincode
400067
Survey no.
Plot no. 807 and CTS no. 3A(pt), Sector-8 of Village- Charkop
North boundary
Private Land
East boundary
plot no 810
South boundary
Plot No 808
West boundary
9 mtr wide DP road
What’s nearby
Schools1 school within 500m
HealthcareHospital 216m away · Clinic within 2km
Lifestyle1 park within 500m
ShoppingSupermarket 1.6km away · Mall 1.6km away
Getting around
Primary road 2.4 km · Goregaon Link RoadRailway line 4.2 kmMetro station 2.5km away (Kandivali (West))Bus stop within 1km
Water & environment
Water body 530 mRiver 583 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Housing and Area Development Authority (MHADA)

Housing Authority
Building Permit
Survey no. Plot no. 807 and CTS no. 3A(pt), Sector-8 of Village- Charkop
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra Housing and Area Development Authority (MHADA)

Planning authority

Has approved 438 RERA projects2.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
341
On record
13,458 flats · 0 plots
Reach
18 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.