HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
21
Buildings
2
Parking
246 spaces
Land area
1,937 sq m
Sanctioned built-up
16,320 sq m

Timeline

RERA registeredMay 2024
Proposed completionDec 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Club House, Fitnes…0%
Excavation63%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Kalpataru Limited

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
10Projects
4Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
358 homeson the public record across 10 projects
2,32,414 sq mbuilt-up filed
62,790 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pune Municipal CorporationMunicipal Corporation4 of 6 projects
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project2 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Andheri
Taluka
Andheri
District
Mumbai Suburban
Pincode
400049
Survey no.
Plot No. 30 CTS No. 195 PT Village Andheri west CTS No. 2 PT of Village Vile Parle West Samarth Ram Das Marg JVPD MHADA Layout, Mumbai
North boundary
CTSNO 195PT of Andheri W
East boundary
12-20 Mt Existing Road
South boundary
18-30 MT Existing Road
West boundary
CTSNo 195PT of Andheri W CTSNo 2PT of Villeparle W
What’s nearby
SchoolsNearest school 1.1km away
HealthcareHospital 197m away · 6 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 836m away · 21+ restaurants and cafes within 1km
ShoppingSupermarket 1.1km away · Mall 1.7km away · Convenience store within 1km
Getting around
Expressway 2.6 km · Andheri FlyoverPrimary road 197 m · Bhakti Vendanta Swami MargRailway line 1.5 kmMetro station 1.6km away (Andheri (West))15 bus stops within 500m
Water & environment
Water body 433 m · Irla Nala
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. Plot No. 30 CTS No. 195 PT Village Andheri west CTS No. 2 PT of Village Vile Parle West Samarth Ram Das Marg JVPD MHADA Layout, Mumbai
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2021
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.