NAKESHA

RERAA KM 27 OF 2023-2024 · RERA Assam · https://gethorizon.in/projects/nakesha-guwahati-kamrup-metro-mpwkn1q9

01

Complete project overview

RERA Assam · Registration filing
Registration category
ONGOINGnew vs ongoing at registration
Land area
2,503 sq m
Local land measure
1bigha4katha7lecha
Parking
76 spaces
RERA validity
31 Dec 2023
Completion
Occupancy / Completion Certificate on record

Timeline

RERA registeredJul 2017
Proposed completionDec 2022
TodaySep 2026
02

Builder’s track record

RERA Assam · Builder registration

NAV SRINATH INFRATECH PVT LTD

CompanyPromoter type
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Assam · Registration filing
District
KAMRUP METRO
Mouza / circle
DISPUR
Town / village
Guwahati
Landmark
Near Repose Bakery
Site address
JILIKA PATH, PANJABARI
Pincode
781037
What’s nearby
SchoolsNearest school 2.0km away · College or university 1.9km away
HealthcareHospital 1.1km away · 3 clinics within 1km
LifestylePark 639m away · Gym or sports centre 1.9km away
ShoppingSupermarket 1.4km away · Mall 1.4km away
Getting around
Expressway 1.9 kmPrimary road 1.3 km · Sixmile FlyoverRailway line 2.1 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 483 mRiver 945 m
distances only — not a flood assessment
04

Government Guidance Rate

Assam registration department

No government guidance rate is shown for this project.

Assam's government guidance rates aren't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RERA Assam · Approved building plan

Guwahati Municipal Corporation

Municipal Corporation
Building Permitapproved 30 Dec 2020 · 5 yrs ago

The promised possession date (31 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Occupancy Certificate — the occupancy sign-off, on record

An Occupancy / Completion Certificateis on this project’s RERA Assam record — the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit and block before you rely on it.

The approving body, at scale

Guwahati Municipal Corporation

Municipal corporation / board

Has approved 604 RERA projectsabout 1 in 1 in Assam, more than any other body in the state.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
488
On record
45,695 flats · 10,758 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RERA Assam

07

Other projects nearby

The register · within 25 km

373 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 467 projects the radar draws within 6 km — every kind, every stage — 180 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

18 projects within 1 km — showing the nearest 6.

SHREENAGARResidential

SHREE SHIVA ENCLAVE PHASE II

M/S SHREE BUILDERS

Mar 2023registered
Mar 2027target completion
Declared cost₹4.64 CrScale91 flatsAuthorityRERA Assam
GUWAHATI

SB RANDIP

S.B. REAL ESTATES AND LANDSCAPES

Dec 2023registered
Jun 2028target completion
Declared cost₹6.13 CrAuthorityRERA Assam
GuwahatiMixed Type

DIZA RESIDENCY

DANIA CONSTRACTIONS, PROP. SYED TASKIR HUSSAIN

Mar 2025registered
Feb 2028target completion
Declared cost₹2.25 CrScale29 flatsAuthorityRERA Assam
GUWAHATIResidential

SAILAJA'S SAPPHIRE

SAILAJA CONSTRUCTION, PROP. MANASH PRATIM TALUKDAR

Oct 2024registered
Oct 2026target completion
Declared cost₹4.71 CrScale12 flatsAuthorityRERA Assam
GUWAHATI

ROYAL EMPIRE

ROYAL CONSTRUCTION

May 2026registered
Mar 2029target completion
AuthorityRERA Assam
GUWAHATI

NJ ZODIAC ENCLAVE

ZODIAC CONSTRUCTION

Apr 2025registered
Dec 2026target completion
Declared cost₹2.41 CrScale64 flatsAuthorityRERA Assam

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Assam does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Assam does not publish a complaints register. This read cannot speak to them either way.