HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
28
Buildings
2
Parking
252 spaces
Land area
5,532 sq m
Sanctioned built-up
16,340 sq m

Timeline

RERA registeredAug 2023
Proposed completionMay 2027
TodayJul 2026
Construction progress
External finishes0%
OC-readiness0%
Energy managemcnt0%
Flat fit-out5%
Fire protection an…10%
Treatment And Disp…50%
Solid Waste Manage…50%
Internal finishes60%
Electrical meter r…70%
Stairs & lifts73%
Sewerage (Chamber,…80%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal Roads & F…100%
Water Supply100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Community Building…100%
Water conservation…100%
Aggregate area of …100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ARDENT PROPERTIES PRIVATE LIMITED

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
2Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
59,628 sq mbuilt-up filed
29,850 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400610
Survey no.
280/2B/2A, 280/2B/2B, 280/2B/2C, 281/2A/1A/1, 281/2A/1A/2, 281/2A/1A/3, 288/2D/1B
North boundary
Tennis Court - Serein
East boundary
Internal Road - Serein
South boundary
Club House - Serein
West boundary
Podium Garden - Serein
What’s nearby
Schools2 schools within 500m · 3 educational institutions within 1km · Library 782m away
HealthcareHospital 242m away · 2 clinics within 1km · Pharmacy within 500m
LifestylePark 694m away · Gym or sports centre 1.3km away · 23+ restaurants and cafes within 1km
ShoppingSupermarket 959m away · Mall 1.6km away · Bank 230m away
Getting around
Expressway 1.5 km · Thane Ghodbunder RoadPrimary road 1.5 km · Eastern Express TurnpikeRailway line 1.9 kmMetro station 1.5km away (Kapurbawdi Station)14 bus stops within 500m
Water & environment
Water body 405 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 280/2B/2A, 280/2B/2B, 280/2B/2C, 281/2A/1A/1, 281/2A/1A/2, 281/2A/1A/3, 288/2D/1B
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.