01

Complete project overview

MahaRERA · Registration filing
Units
29 units
Floors
14
Buildings
2
Parking
39 spaces
Land area
609 sq m
Sanctioned built-up
2,988 sq m

Timeline

RERA registeredSep 2026
Proposed completionDec 2030
TodaySep 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Storm Water Drains0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SMK DEVLOPERS LLP

Limited Liability PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bandra
Taluka
Andheri
District
Mumbai Suburban
Pincode
400054
Survey no.
PLOT NO. 60, C.T.S. NO. 366-A
North boundary
Plot No. D5 OF GUZDAR SCHEME AND PLOT NO. 60A;
East boundary
Linking Road,
South boundary
North Avenue Road,
West boundary
Dev Pooja CHSL;
What’s nearby
Schools2 schools within 500m · 3 educational institutions within 1km · College or university 1.6km away
HealthcareHospital 353m away · 10 clinics within 1km · Pharmacy within 1km
LifestylePark 961m away · Playground within 500m · Gym or sports centre 697m away
ShoppingSupermarket 236m away · Convenience store within 1km · Bank 24m away
Getting around
Expressway 1.3 kmPrimary road 320 m · Swami Vivekanand RoadRailway line 692 mRailway station 810m away (Santa Cruz)9 bus stops within 500m
Water & environment
Water body 626 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. PLOT NO. 60, C.T.S. NO. 366-A
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,638 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,023 projects the radar draws within 6 km — every kind, every stage — 759 are residential projects still under way. This list keeps only those, and looks further out.

62 projects within 1 km — showing the nearest 6.

40 m awayOthers

Sheetal Inder Mohini

D.G.S LAND DEVELOPERS (INDIA) PRIVATE LIMITED · Bandra · Andheri

Jan 2024registered
Dec 2026target completion
1 open complaintScale38 flatsAuthorityMahaRERA
40 m awayResidential / Group Housing

54 Park Lane

L NAGPAL BUILDCON LLP · Bandra · Andheri

Dec 2025registered
Dec 2028target completion
Scale25 flatsAuthorityMahaRERA
40 m awayResidential / Group Housing

Titanium Rajshree

ORANGE INFRA HOUSING LLP · Bandra · Andheri

May 2026registered
Nov 2028target completion
Government Guidance Rate₹3,35,304/sq ydScale32 flatsAuthorityMahaRERA
40 m awayResidential / Group Housing

Santacruz Aster Co-Op Housing Society Limited

Vira Platinum LLP · Bandra · Andheri

Jan 2026registered
Mar 2028target completion
Scale30 flatsAuthorityMahaRERA
100 m awayResidential / Group Housing

GARDEN CREST

VBHDC BANGALORE VALUE HOMES PRIVATE LIMITED · Danda · Andheri

Feb 2025registered
Dec 2027target completion
Scale23 flatsAuthorityMahaRERA
120 m awayOthers

PEARL QUEEN

PEARL QUEEN COOPERATIVE HOUSING SOCIETY LIMITED · Bandra · Andheri

Jul 2024registered
Jun 2029target completion
Scale30 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Escrow — MahaRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.