Sukhwani Ambar

P52100026576 · MahaRERA · https://gethorizon.in/projects/sukhwani-ambar-wakad-mulshi-5qd2nt20

01

Complete project overview

MahaRERA · Registration filing
Project name
Sukhwani Ambar
Units
358 units
Floors
23
Buildings
9
Parking
212 spaces
Land area
11,304 sq m
Sanctioned built-up
34,292 sq m
Recreational open space
988 sq m

Timeline

RERA registeredOct 2020
Proposed completionJun 2027
TodaySep 2026
Construction progress
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Flat fit-out5%
Internal finishes40%
Superstructure70%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor1001%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SUKHWANI DEVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
2Cities
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
452 homeson the public record across 2 projects
39,331 sq mbuilt-up filed
13,583 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SUKHWANI DEVELOPERS— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Wakad
Taluka
Mulshi
District
Pune
Pincode
411057
Survey no.
84/3A,85/1/1,85/1/2,85/2A,85/2B,85/3/1,85/3/2,86/2/A,86/2/B/1
North boundary
By Survey no 91
East boundary
By Project - Sonasta on part S No 86
South boundary
By Road
West boundary
By Project Nisarg Siddhi on part S No 84
What’s nearby
Schools1 school within 1km · College or university 1.6km away
HealthcareHospital 140m away · 4 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 124m away · 18+ restaurants and cafes within 1km
ShoppingSupermarket 625m away · Mall 1.6km away · Bank 314m away
Getting around
Expressway 2.1 kmPrimary road 359 m · Shree Chatrapati Shivaji Maharaj FlyoverRailway line 3.2 km · Mumbai–Pune RailwayMetro station 3.0km away (Wakad Chowk metro Station)Bus stop within 1km
Water & environment
Water body 961 m · Swimming Pool
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹68,746per sq yd
₹82,220per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Wakad”.
In force
2026-2027 schedule
Spread
₹41,397₹86,957 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 84/3A,85/1/1,85/1/2,85/2A,85/2B,85/3/1,85/3/2,86/2/A,86/2/B/1
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,238 residential projects still under way within 25 km. Step out ring by ring:

Of the 2,084 projects the radar draws within 6 km — every kind, every stage — 688 are residential projects still under way. This list keeps only those, and looks further out.

12 projects within 1 km — showing the nearest 6.

140 m awayResidential / Group Housing

SIGNATURE PARK E F I AND J BUILDINGS

SHREE SONIGARA REALCON · Thergaon · Mulshi

Dec 2020registered
Jun 2026target completion
44 open complaintsGovernment Guidance Rate₹70,134/sq ydScale360 flatsAuthorityMahaRERA
220 m awayResidential / Group Housing

Greens - Oak - OP

AMJ Land Developers · Thergaon · Mulshi

Oct 2023registered
Dec 2027target completion
Government Guidance Rate₹70,134/sq ydScale128 flatsAuthorityMahaRERA
280 m awayOthers

SIGNATURE RITZ

SHREE SONIGARA REALCON · Thergaon · Mulshi

Jul 2023registered
Dec 2028target completion
1 open complaintGovernment Guidance Rate₹70,134/sq ydScale288 flatsAuthorityMahaRERA
290 m awayResidential / Group Housing

SIGNATURE PARK K L N BUILDINGS

SHREE SONIGARA REALCON · Thergaon · Mulshi

Mar 2026registered
Dec 2029target completion
Government Guidance Rate₹70,134/sq ydScale408 flatsAuthorityMahaRERA
390 m awayResidential / Group Housing

Urban Skyline Phase I

Urban Space Creators · Ravet · Haveli

Sep 2020registered
Jun 2027target completion
Government Guidance Rate₹57,684/sq ydScale414 flatsAuthorityMahaRERA
450 m awayResidential / Group Housing

Aeternaa - C Wing Phase 1

KORELH REALLTECH LLP · Thergaon · Mulshi

Jul 2024registered
Dec 2027target completion
Government Guidance Rate₹70,134/sq ydScale76 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.