Complete project overview

MahaRERA · Registration filing
Floors
18
Buildings
2
Parking
119 spaces
Land area
1,290 sq m
Sanctioned built-up
3,616 sq m

Timeline

RERA registeredSep 2021
Proposed completionDec 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
OC-readiness92%
Fire protection an…98%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Water conservation…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

LAXMI CONSTRUCTION CO

PartnershipPromoter type
Thane, MAHARASHTRABased in
3Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
93 homeson the public record across 3 projects
11,968 sq mbuilt-up filed
6,345 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kalyan-Dombivali (M Corp.)
Taluka
Kalyan
District
Thane
Pincode
421301
Survey no.
SURVEY NO.36, HISSA NO.3/1
North boundary
Survey No 36 Hissa No 4
East boundary
Land owned by Raghunath Jadhav and Others
South boundary
Survey No 36 Hissa No 1 and 4
West boundary
Land owned by Sukanya Ganpath Kene
What’s nearby
SchoolsNearest school 1.5km away · College or university 599m away
HealthcareHospital 233m away · 2 clinics within 1km
LifestylePark 1.8km away
ShoppingSupermarket 763m away
Getting around
Expressway 344 mPrimary road 1.6 km · Kalyan-Murbad RoadRailway line 1.7 km · Mumbai–Nagpur RailwayRailway station 2.2km away (Shahad)Limited bus connectivity nearby
Water & environment
Water body 973 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO.36, HISSA NO.3/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 0 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.