HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
37
Buildings
2
Parking
324 spaces
Land area
3,910 sq m
Sanctioned built-up
18,537 sq m

Timeline

RERA registeredJul 2024
Proposed completionMar 2029
TodayJul 2026
Construction progress
Basement (if any)0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Water conservation…0%
Fire protection an…0%
Internal finishes2%
Superstructure19%
Podiums80%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHAKTI REALTY

PartnershipPromoter type
Thane, MAHARASHTRABased in
8Projects
3Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
8 projectson the public record across 8 projects
86,776 sq mbuilt-up filed
36,590 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Bhiwandi Nizampur Municipal CorporationMunicipal Corporation4 of 7 projects
Mumbai Metropolitan Region Development AuthorityMetropolitan Development Authority2 of 7 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporationthis project1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
District
Thane
Pincode
421301
Survey no.
SURVEY NO. 55, H.NO. 3, SURVEY NO. 41, H.NO. 11, SURVEY NO. 42, H. NO. 1A & 1B
North boundary
6 MTR WIDE ROAD
East boundary
BUILDING B1 AND SURVEY NO 55
South boundary
PLAYGROUND
West boundary
30 MTR AND 18 MTR DP ROAD
What’s nearby
SchoolsNearest school 1.6km away · College or university 538m away
HealthcareHospital 162m away · 2 clinics within 1km
LifestylePark 1.8km away
ShoppingSupermarket 690m away
Getting around
Expressway 467 mPrimary road 1.7 km · Kalyan-Murbad RoadRailway line 1.8 kmRailway station 2.3km away (Shahad)Limited bus connectivity nearby
Water & environment
Water body 951 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO. 55, H.NO. 3, SURVEY NO. 41, H.NO. 11, SURVEY NO. 42, H. NO. 1A & 1B
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.