HORIZON
Share

VERVE MANSION

P51900046224 · MahaRERA · https://gethorizon.in/projects/verve-mansion-mumbai-city-dk8xul8g

01

Complete project overview

MahaRERA · Registration filing
Units
99 units
Floors
27
Buildings
2
Parking
77 spaces
Land area
1,314 sq m
Sanctioned built-up
1,747 sq m

Timeline

RERA registeredJun 2022
Proposed completionDec 2027
TodaySep 2026
Construction progress
Flat fit-out0%
OC-readiness0%
Water Supply0%
Water conservation…0%
Electrical meter r…30%
External finishes40%
Fire protection an…55%
Internal finishes60%
Stairs & lifts95%
Sewerage (Chamber,…99%
Storm Water Drains99%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SHANTI SIDDHI INFRA LLP

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mumbai City
Taluka
Mumbai City
District
Mumbai City
Pincode
400019
Survey no.
373/10,374/10
North boundary
Plot No 458
East boundary
Plot No 452 And 453
South boundary
Plot No 461C
West boundary
Bhau Dhaji Road
What’s nearby
Schools6 schools within 1km · 6 educational institutions within 1km · College or university 1.4km away
HealthcareHospital 321m away · 8 clinics within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · Gym or sports centre 1.4km away · 33+ restaurants and cafes within 1km
ShoppingSupermarket 319m away · Mall 615m away · Convenience store within 500m
Getting around
Expressway 319 m · Laxmibai Kelkar MargPrimary road 319 m · Rafi Ahmed Kidwai MargRailway line 185 m · Central Railway (Express)Railway station 345m away (King's Circle)8 bus stops within 500m
Water & environment
Water body 1.5 km · tank
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 373/10,374/10
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

3,624 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,872 projects the radar draws within 6 km — every kind, every stage — 645 are residential projects still under way. This list keeps only those, and looks further out.

41 projects within 1 km — showing the nearest 6.

SionResidential / Group Housing

Bellissimo Matunga

Lodha Developers Limited

Feb 2023registered
Dec 2027target completion
Scale148 flatsAuthorityMahaRERA
SionResidential / Group Housing

Bellissimo Matunga-Tower 2

Lodha Developers Limited

Jun 2023registered
Dec 2027target completion
Scale116 flatsAuthorityMahaRERA
SionResidential / Group Housing

Bellissimo Matunga-Tower 3

Lodha Developers Limited

Jun 2023registered
Dec 2027target completion
Scale107 flatsAuthorityMahaRERA
Salt Pan DivisionResidential / Group Housing

Lodha Matunga

Lodha Developers Limited

Aug 2023registered
Apr 2028target completion
Scale58 flatsAuthorityMahaRERA
Fnorth-400019Others

BELLWETHER AMARI

BELLWETHER INFRASTRUCTURE LLP

May 2024registered
Jun 2027target completion
Scale31 flatsAuthorityMahaRERA
WadalaResidential / Group Housing

Godrej Horizon Phase III

Godrej Projects Development Ltd

Dec 2024registered
Jun 2031target completion
Scale362 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.