Complete project overview

K-RERA · Registration filing
Buildings
9
Land area
1,378 sq m
Description
VICTORIA REALTORS CHAITHRAM THIRD PHASE

Timeline

Project startedJan 2021
RERA registeredJul 2021
Proposed completionJan 2023
TodayJul 2026
Construction progress

86% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

K-RERA · Promoter registration

DHARMIC LIVING PVT LTD

CompanyPromoter type
Palakkad, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
36Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
560 plotson the public record across 36 projects
1,52,414 sq mplotted area
1,52,414 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Avanur Grama Panchayath ThrissurLocal body (LSGI)2 of 36 projects
Mundur Grama PanchayatGrama Panchayatthis project2 of 36 projects
Parali Grama PanchayatGrama Panchayat2 of 36 projects
Velur Grama Panchayath ThrissurLocal body (LSGI)2 of 36 projects
Akathethara Grama Panchayath PalakkadLocal body (LSGI)1 of 36 projects
Ambalapara Grama Panchauat PalakkadLocal body (LSGI)1 of 36 projects
Ambalapara Grama PanchayatGrama Panchayat1 of 36 projects
Ambalapara Grama Panchayat PalakkadLocal body (LSGI)1 of 36 projects
Avinissery Grama Panchayath ThrissurLocal body (LSGI)1 of 36 projects
Elapully Grama PanchayatGrama Panchayat1 of 36 projects
Kaiparamb Grama Panchayat ThrissurLocal body (LSGI)1 of 36 projects
Kaiparamb Grama Panchayath ThrissurLocal body (LSGI)1 of 36 projects
Kaiparambu Grama Panchayat ThrissurLocal body (LSGI)1 of 36 projects
Kannadi Grama Panchayath PalakakdLocal body (LSGI)1 of 36 projects
Ottapalam MuncipalityLocal body (LSGI)1 of 36 projects
Parali Grama Panchayat PalakakdLocal body (LSGI)1 of 36 projects
Parali Grama Panchayath PalakkadLocal body (LSGI)1 of 36 projects
Pirayiri Grama PanchayatGrama Panchayat1 of 36 projects
Pirayiri PanchayathLocal body (LSGI)1 of 36 projects
Secretary Parali Grama Panchayath PalakkadLocal body (LSGI)1 of 36 projects
Sreekrishnapuram Grama PanchayatGrama Panchayat1 of 36 projects
Sreekrishnapuram Grama Panchayath PalakkadLocal body (LSGI)1 of 36 projects
Thiruvananthapuram Municipal CorporationMunicipal Corporation1 of 36 projects
Thiruvaniyoor Grama Panchayath ErnakulamLocal body (LSGI)1 of 36 projects
Tholur Grama PanchayatGrama Panchayat1 of 36 projects
Thrissur Muncipal Corporation ThrissurLocal body (LSGI)1 of 36 projects
Valamkulam Grama Panchayath PalakakdLocal body (LSGI)1 of 36 projects
Vaniamkulam Grama Panchayath PalakkadLocal body (LSGI)1 of 36 projects
Vaniyamkulam Grama Panchayath OttapalamLocal body (LSGI)1 of 36 projects
Velukkara Grama PanchayatGrama Panchayat1 of 36 projects
Velur Grama PanchayatGrama Panchayat1 of 36 projects
Velur Grama Panchayat ThrissurLocal body (LSGI)1 of 36 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
MUNDUR
Village
MUNDUR I
Taluk
Palakkad
District
Palakkad
Pincode
678592
Survey no.
475/77, 475/80, 475/78, 475/82, 475/81, 475/79, 475/83,
Patta no.
5486
What’s nearby
SchoolsNearest school 1.1km away · 3 educational institutions within 1km · Library 102m away
HealthcareHospital 443m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · ATM within 500m
Getting around
Expressway 162 m · Palakkad-Mannarkkad-Calicut RoadPrimary road 281 m · Palakkad-Perintalmanna RoadRailway line 3.3 kmRailway station 4.4km away (Parali)Bus stop within 500m
Water & environment
Water body 138 mCanal 1.2 km · Malampuzha Canal
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Mundur Grama Panchayat

Grama Panchayat
approved 14 Sep 2021 · 4 yrs ago
Layout Permit no. A4-BA(196652)/2021Survey no. 475/77, 475/80, 475/78, 475/82, 475/81, 475/79, 475/83,

The promised possession date (9 Jan 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A4-BA(196652)/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Grama Panchayat

A village-level local self-government (LSGI) that issues the permit — Kerala's most common approving body. It has approved 268 RERA projects across 13 districts about 1 in 6 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.