HORIZON
Share

VICTORIA REALTORS VANDHANAM

T1/OL/124/2022 · K-RERA · https://gethorizon.in/projects/victoria-realtors-vandhanam-velur-thrissur-8lwx1n07

01

Complete project overview

K-RERA · Registration filing
Project name
VICTORIA REALTORS VANDHANAM
Plots
1 plots
Mix
1 × Bangalow / Villas
Booked
32 of 1 filed sold/bookedas declared in the RERA filing
Buildings
16
Land area
4,503 sq m
Floor area
2,000 sq m
Description
VICTORIA REALTORS VANDHANAM

Timeline

Project startedMay 2022
RERA registeredMay 2022
Proposed completionApr 2025
TodaySep 2026
Construction progress

79% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Electrical Fittings10%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings20%
Overhead and Underground Water Tanks.80%
Staircases, Lifts Wells80%
Overhead and Underground Water Tanks.80%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

0 of 1 available
TypeArea sq mAvailable
Bangalow / Villas1230 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.

02

Builder’s track record

K-RERA · Builder registration

DHARMIC LIVING PVT LTD

CompanyPromoter type
Thrissur, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
39Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
637 plotson the public record across 39 projects
1,70,807 sq mplotted area
1,70,807 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Avanur Grama Panchayath ThrissurLocal body (LSGI)2 of 39 projects
Mundur Grama PanchayatGrama Panchayat2 of 39 projects
Parali Grama PanchayatGrama Panchayat2 of 39 projects
Velur Grama Panchayath ThrissurLocal body (LSGI)2 of 39 projects
Akathethara Grama Panchayath PalakkadLocal body (LSGI)1 of 39 projects
Ambalapara Grama Panchauat PalakkadLocal body (LSGI)1 of 39 projects
Ambalapara Grama PanchayatGrama Panchayat1 of 39 projects
Ambalapara Grama Panchayat PalakkadLocal body (LSGI)1 of 39 projects
Avanur Grama Panchayat ThrissurLocal body (LSGI)1 of 39 projects
Avinissery Grama Panchayath ThrissurLocal body (LSGI)1 of 39 projects
Elapully Grama PanchayatGrama Panchayat1 of 39 projects
Kaiparamb Grama Panchayat ThrissurLocal body (LSGI)1 of 39 projects
Kaiparamb Grama Panchayath ThrissurLocal body (LSGI)1 of 39 projects
Kaiparambu Grama Panchayat ThrissurLocal body (LSGI)1 of 39 projects
Kannadi Grama Panchayath PalakakdLocal body (LSGI)1 of 39 projects
Kottayi Grama PanchayatGrama Panchayat1 of 39 projects
Kuzhalmannam Grama PanchayatGrama Panchayat1 of 39 projects
Ottapalam MuncipalityLocal body (LSGI)1 of 39 projects
Parali Grama Panchayat PalakakdLocal body (LSGI)1 of 39 projects
Parali Grama Panchayath PalakkadLocal body (LSGI)1 of 39 projects
Pirayiri Grama PanchayatGrama Panchayat1 of 39 projects
Pirayiri PanchayathLocal body (LSGI)1 of 39 projects
Secretary Parali Grama Panchayath PalakkadLocal body (LSGI)1 of 39 projects
Sreekrishnapuram Grama PanchayatGrama Panchayat1 of 39 projects
Sreekrishnapuram Grama Panchayath PalakkadLocal body (LSGI)1 of 39 projects
Thiruvananthapuram Municipal CorporationMunicipal Corporation1 of 39 projects
Thiruvaniyoor Grama Panchayath ErnakulamLocal body (LSGI)1 of 39 projects
Tholur Grama PanchayatGrama Panchayat1 of 39 projects
Thrissur Muncipal Corporation ThrissurLocal body (LSGI)1 of 39 projects
Valamkulam Grama Panchayath PalakakdLocal body (LSGI)1 of 39 projects
Vaniamkulam Grama Panchayath PalakkadLocal body (LSGI)1 of 39 projects
Vaniyamkulam Grama Panchayath OttapalamLocal body (LSGI)1 of 39 projects
Velukkara Grama PanchayatGrama Panchayat1 of 39 projects
Velur Grama PanchayatGrama Panchayatthis project1 of 39 projects
Velur Grama Panchayat ThrissurLocal body (LSGI)1 of 39 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from DHARMIC LIVING PVT LTD— the full portfolio →

03

Location

K-RERA · Registration filing
Street
MUNDUR
Village
VELUR
Taluk
KUNNAMKULAM
District
Thrissur
Pincode
680601
Survey no.
705/PT19, 705/PT18, 705/PT11
Patta no.
8341
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km · College or university 2.0km away
HealthcareHospital 232m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 921m away · 4 restaurants and cafes within 1km
ShoppingSupermarket 181m away · Mall 376m away · Convenience store within 500m
Getting around
Primary road 123 mRailway line 2.3 km · Guruvayur-Thrissur LineRailway station 3.7km away (Amalanagar)2 bus stops within 500m
Water & environment
Water body 250 mCanal 1.0 kmRiver 1.6 km
distances only — not a flood assessment
04

Government Guidance Rate

Kerala Registration Department — fair value

In Kerala it’s called the fair value.

₹654per sq yd
₹783per sq m
Which rate
Residential Plot with Corp./Mun./Panch. road access
Matched to
The value published for this project's own survey number, in “Velur”.

What this number is — and isn’t

  • The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of parcel, and says so above. How Horizon decides what to show.
05

Planning authority

K-RERA · Approved building plan

Velur Grama Panchayat

Grama Panchayat
approved 26 Apr 2022 · 4 yrs ago
Layout Permit no. A4-BA(137717)/2022Survey no. 705/PT19, 705/PT18, 705/PT11

The promised possession date (30 Apr 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan A4-BA(137717)/2022 on the approving authority’s portal to confirm the approval.

The approving body, at scale

Grama Panchayat

A village-level local self-government (LSGI) that issues the permit — Kerala's most common approving body. It has approved 268 RERA projects across 13 districts about 1 in 6 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

29 plotted projects still under way within 25 km. Step out ring by ring:

Of the 35 projects the radar draws within 6 km — every kind, every stage — 14 are plotted projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

540 m awayPlots

VICTORIA REALTORS NANDANAM

DHARMIC LIVING PVT LTD · ANJOOR THRISSUR

Dec 2023registered
Dec 2028target completion
Scale9 plotsAuthorityK-RERA
800 m awayPlots

VICTORIA REALTORS PRIYAM

DHARMIC LIVING PVT LTD · PERAMANGALAM

Jul 2024registered
Jun 2029target completion
Government Guidance Rate₹2,428/sq ydScale14 plotsAuthorityK-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.