Complete project overview

RERA Telangana · Registration filing
Units
30 units
Unit mix
20 × 2BHK, 10 × 3BHK
Saleable area
106–150 sq mper unit, as filed
Floors
5
Land area
1,711 sq m
Built-up area
5,196 sq m

Timeline

RERA approvedJun 2024
Proposed completionJun 2027
TodayJul 2026
Construction progress

53% overall, as filed

Podiums0%
Flat fit-out0%
OC-readiness0%
Stairs & lifts30%
Internal finishes50%
External finishes60%
Stilt floor90%
Excavation100%
Basement & plinth100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

25 of 30 available
BuildingFloorTypeArea sq mAvailable
Aarna13BHK1451 of 1
Aarna12BHK1061 of 1
Aarna12BHK1201 of 1
Aarna12BHK1091 of 1
Aarna12BHK1331 of 1
Aarna13BHK1501 of 1
Aarna23BHKmortgaged1451 of 1
Aarna22BHKmortgaged1061 of 1
Aarna22BHKmortgaged1201 of 1
Aarna22BHKmortgaged1091 of 1
Aarna22BHKmortgaged1331 of 1
Aarna23BHKmortgaged1501 of 1
Aarna32BHK1061 of 1
Aarna32BHK1091 of 1
Aarna32BHK1331 of 1
Aarna33BHK1450 of 1
Aarna32BHK1200 of 1
Aarna33BHK1500 of 1
Aarna43BHK1451 of 1
Aarna42BHK1061 of 1
Aarna42BHK1331 of 1
Aarna43BHK1501 of 1
Aarna42BHK1090 of 1
Aarna42BHK1200 of 1
Aarna53BHK1451 of 1
Aarna52BHK1061 of 1
Aarna52BHK1201 of 1
Aarna52BHK1091 of 1
Aarna52BHK1331 of 1
Aarna53BHK1501 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI GAYATRI PROJECTS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
2Projects
2Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
45 homeson the public record across 2 projects
7,429 sq mbuilt-up filed
2,455 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Ibrahimbagh 7b
Mandal
Golconda
District
Hyderabad
Pincode
500031
North boundary
OTHERS LAND
East boundary
OTHERS LAND
South boundary
ROAD
West boundary
OTHERS LAND
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.4km away
HealthcareHospital 756m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 1.5km away · Gym or sports centre 863m away · Swimming pool within 2km
ShoppingSupermarket 336m away · Bank 838m away
Getting around
Expressway 3.2 kmPrimary road 1.9 kmMetro station 4.9km away (Peddamma Gudi)Limited bus connectivity nearby
Water & environment
Water body 978 m · Pedda Cheruvu
distances only — not a flood assessment
Declared external development
Green Strip/TOT LO…70%
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 128 & 129
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.