HORIZON
Share

Anand Homes- Phase 2

P51700053225 · MahaRERA · https://gethorizon.in/projects/anand-homes-phase-2-titwala-kalyan-jpjkpc33

Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
139 units
Floors
8
Buildings
4
Parking
127 spaces
Land area
5,761 sq m
Sanctioned built-up
5,761 sq m

Timeline

RERA registeredOct 2023
Proposed completionJun 2026
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

M/s. MORYA GROUP

PartnershipPromoter type
Thane, MAHARASHTRABased in
3Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
443 homeson the public record across 3 projects
17,942 sq mbuilt-up filed
17,942 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from M/s. MORYA GROUP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Titwala
Taluka
Kalyan
District
Thane
Pincode
421605
Survey no.
78/1 & 79
North boundary
80
East boundary
77
South boundary
78-2
West boundary
79
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 450m away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.5 km · Kalyan - A'Nagar RoadPrimary road 131 m · Titwala - Ambivli RoadRailway line 1.1 kmRailway station 2.0km away (Titwala)Limited bus connectivity nearby
Water & environment
Water body 119 mRiver 641 m · Kalu
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹43,729per sq yd
₹52,300per sq m
Which rate
residential flat (built)
Matched to
The rate published for the village of “Titwala”.
In force
2026-2027 schedule

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Kalyan Dombivli Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 78/1 & 79

The promised possession date (1 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Kalyan Dombivli Municipal Corporation

Municipal corporation

Has approved 742 RERA projects3.7% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
585
On record
5,683 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

1,571 residential projects still under way within 25 km. Step out ring by ring:

Of the 210 projects the radar draws within 6 km — every kind, every stage — 54 are residential projects still under way. This list keeps only those, and looks further out.

9 projects within 1 km — showing the nearest 6.

30 m awayOthers

SHREE GAJANAN HEIGHTS

R K CONSTRUCTION · Titwala · Kalyan

Jan 2020registered
Dec 2026target completion
Government Guidance Rate₹43,729/sq ydScale11 flatsAuthorityMahaRERA
100 m awayResidential / Group Housing

Vedant Millenia Happiness Phase II Wing E

MOHAN HARDASMAL THARWANI · Titwala · Kalyan

Nov 2022registered
Dec 2026target completion
Government Guidance Rate₹43,729/sq ydScale55 flatsAuthorityMahaRERA
100 m awayResidential / Group Housing

Vedant Millenia happiness Phase II Wing C

MOHAN HARDASMAL THARWANI · Titwala · Kalyan

Mar 2023registered
Dec 2027target completion
Government Guidance Rate₹43,729/sq ydScale197 flatsAuthorityMahaRERA
100 m awayOthers

Vedant Millenia Happiness Phase II Wing D

MOHAN HARDASMAL THARWANI · Titwala · Kalyan

Mar 2024registered
Jul 2028target completion
Government Guidance Rate₹43,729/sq ydScale25 flatsAuthorityMahaRERA
130 m awayOthers

MARATHE SAPPHIRE

SAIJI DEVELOPERS · Titwala · Kalyan

Feb 2022registered
Dec 2031target completion
Government Guidance Rate₹43,729/sq ydScale185 flatsAuthorityMahaRERA
260 m awayOthers

SHREE VIGHNESHWAR HEIGHTS

MAHESH SHYAMSUNDAR GOYAL · Titwala · Kalyan

Aug 2021registered
Mar 2027target completion
Government Guidance Rate₹43,729/sq ydScale185 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.