Complete project overview

RAJ-RERA · Registration filing
Land area
7,571 sq m
Completion deadline extended
1 extension on record — latest to 31 May 2022declared reason: force majeure

Timeline

Construction startDec 2017
RERA registeredDec 2017
Proposed completionMay 2021
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

VIVEK CHORDIA

IndividualPromoter type
Jaipur, RajasthanBased in
6Projects
1City
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
184 homeson the public record across 6 projects
69,185 sq mbuilt-up filed
28,590 sq mland declared
₹149.81 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
GH-1, Chordia City II, Ajmer Road, Jaipur, Sanganer, Jaipur, 302006
Village
Jaipur
Taluka
Sanganer
District
Jaipur
Pincode
302006
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 891m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.4 kmPrimary road 4.5 kmRailway line 4.8 kmMetro station 4.7km away (Manasarovar)Limited bus connectivity nearby
Water & environment
Water body 4.0 km · Fountain RD
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹55.40 Cr declared. What that works out to:

9%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 26 Dec 2017 · 8 yrs ago

The promised possession date (31 May 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.