01

Complete project overview

RAJ-RERA · Registration filing
Land area
5,900 sq m
Description
1. As per Township Policy 2010, 5 Plots (Plot No.20 TO 24 ) having Total area of 509.98 Sq. Mtrs equalling to 12.5% have been kept mortgage. These plots would be allotted after the internal development work is completed and development charges are deposited with Jaipur Development Authority, Jaipur.

Timeline

RERA registeredDec 2021
Construction startJan 2022
Proposed completionDec 2024
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

SHIV MANORAMA BUILD ESTATE PRIVATE LIMITED

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2021–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
298/153,301/154, Near Patrkar Colony, Ramsinghpura, Jaipur, Jaipur, 303108
Village
Ramsinghpura
Taluka
Jaipur
District
Jaipur
Pincode
303108
What’s nearby
SchoolsNearest school 1.4km away · College or university 1.1km away
HealthcareHospital 1.1km away · 1 clinic within 1km
LifestylePark 1.9km away
ShoppingNo supermarket within 2km
Getting around
Expressway 1.0 kmPrimary road 1.8 km · B2 BypassRailway line 3.3 km · Jaipur to Sawai Madhopur LineMetro station 3.4km away (Manasarovar)Limited bus connectivity nearby
Water & environment
Water body 2.8 km · Dravyavati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹2.21 Cr declared. What that works out to:

₹348/sq ftof plotted area₹3,748/sq m
59%of the cost is land₹207/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Layout Permitapproved 31 Dec 2021 · 4 yrs ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RAJ-RERA

07

Other projects nearby

The register · within 25 km

235 plotted projects still under way within 25 km. Step out ring by ring:

Of the 543 projects the radar draws within 6 km — every kind, every stage — 69 are plotted projects still under way. This list keeps only those, and looks further out.

7 projects between 1 and 3 km — showing the nearest 6.

1.5 km awayPlotted Development

Laxmi Villa

SURESH PRAJAPATI · Sanganer · Jaipur

Jan 2025registered
Jul 2026target completion
possession revisedDeclared cost₹1.84 CrScale42 plotsAuthorityRAJ-RERA
1.5 km awayPlotted Development

ROOP NAGAR

LAL CHAND CHOUDHARY · Sanganer · Jaipur

May 2025registered
Nov 2026target completion
Declared cost₹10.08 CrScale15 plotsAuthorityRAJ-RERA
1.5 km awayPlotted Development

RAGHAV TOWN CROWN

NITIN KEDIA · Sanganer · Jaipur

Nov 2025registered
Dec 2026target completion
Declared cost₹24.13 CrScale100 plotsAuthorityRAJ-RERA
1.8 km awayPlotted Development

SHANTI NAGAR

MANISH MITTAL · Sanganer · Jaipur

May 2023registered
Mar 2027target completion
possession revisedDeclared cost₹6.50 CrScale112 plotsAuthorityRAJ-RERA
2.6 km awayPlotted Development

Farm House Scheme

RAJASTHAN HOUSING BOARD · Sanganer · Jaipur

May 2022registered
Dec 2027target completion
Declared cost₹4.15 CrScale8 plotsAuthorityRAJ-RERA
2.7 km awayPlotted Development

Govindam Greens

Shyam Sarkar Builders and Developers · Sanganer · Jaipur

Mar 2025registered
Aug 2026target completion
Declared cost₹5.96 CrScale61 plotsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.