Complete project overview

RAJ-RERA · Registration filing
Units
39 units
Mix
13 × Unit No. 101, 201, 301, 401, 501, 601, 701, 801, 901, 1001, 1101, 1201, 1301 · 13 × Unit No. 102, 202, 302, 402, 502, 602, 702, 802, 902, 1002, 1102, 1202, 1302 · 13 × Unit No. 103, 203, 303, 403, 503, 603, 703, 803, 903, 1003, 1103, 1203, 1303
Carpet area
28–38 sq mper-type range, as filed
Land area
8,211 sq m
Completion deadline extended
4 extensions on record — latest to 31 Aug 2023declared reason: other than force majeure
Description
1. SUWALKA RIDDHI SIDDHI APARTMENT IS OUR ONGOING PROJECT HAVING LAND AREA OF 8211.39 SQ. METERS. WE SUBMITTED RERA APPLICATION FEE OF RS.82114/- VIDE PAYMENT ID 81177222 TRAN NO.RERA-TRANS-1857 ON DATED 07-08-2017 TIME 20:50:14. AGAIN AS PER RERA CIRCULAR P.(4)RJ/RERA/2017/D-27, DATED 10-08-2017, WE PAID RS.3,28,456/- VIDE DD NO.038648 HDFC BANK DATED 24-08-2017 AS LATE SUBMISSION FEE AT UR OFFICE. SO TOTAL WE PAID 4,10,570/- AGAINST RERA CERTIFICATION FEE. THE ESTIMATED FINISH DATE OF THE PROJECT WAS EXTENDED ON 10-02-2020. THIS BEARS THE APPROVAL OF HONORABLE CHAIRMAN, BEFORE EXTENSION THE ESTIMATED FINISH DATE WAS 19-11-2019. 2. WITH THE PERMISSION OF RERA, PROJECT NAME HAS BEEN CHANGED FROM "SUWALKA RIDDHI SIDDHI APARTMENT" TO "MERIDIAN HEIGHTS"; AND ALL DECLARATIONS, UNDERTAKINGS, AGREEMENTS AND OTHER DOCUMENTS EXECUTED BY THE PROMOTER WITH "SUWALKA RIDDHI SIDDHI APARTMENT" AS THE NAME OF THIS PROJECT WILL CONTINUE TO HOLD GOOD FOR THIS PROJECT NOW NAMED AS "MERIDIAN HEIGHTS "

Timeline

Construction startNov 2015
RERA registeredSep 2017
Proposed completionNov 2020
TodayJul 2026

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

39 units across 3 batches
BuildingTypeArea sq mCount
SUWALKA RIDDHI SIDDHI APARTMENTUnit No. 101, 201, 301, 401, 501, 601, 701, 801, 901, 1001, 1101, 1201, 13013813
SUWALKA RIDDHI SIDDHI APARTMENTUnit No. 102, 202, 302, 402, 502, 602, 702, 802, 902, 1002, 1102, 1202, 13023813
SUWALKA RIDDHI SIDDHI APARTMENTUnit No. 103, 203, 303, 403, 503, 603, 703, 803, 903, 1003, 1103, 1203, 13032813

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

PRANAY INFRA BUILD P L

OrganisationPromoter type
Kota, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
PLOT NO."B", K.N.23 (PART), BUNDI ROAD, GRAM KUNHARI, KOTA, RAJASTHAN, KOTA, Ladpura, Kota, 324008
Village
KOTA
Taluka
Ladpura
District
Kota
Pincode
324008
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.3km away
LifestylePark 869m away
ShoppingNo supermarket within 2km · Bank 882m away
Getting around
Primary road 72 m · Boondi Road FlyoverRailway line 374 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Canal 1.5 kmRiver 1.7 km · Chambal River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹112.51 Cr declared to build 39 flats. What that works out to:

₹2.88 Crdeclared cost per flatall-in — land + construction
₹2,368/sq ftof built-up area₹25,492/sq m
2%of the cost is land₹284/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 8 Sep 2017 · 8 yrs ago

The promised possession date (19 Nov 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.