HORIZONMarkets
01

Complete project overview

JHARERA · Registration filing
Units
14 units
Carpet area
91–255 sq mper unit, as filed
Parking
14 spaces14 covered · 0 open
Amenities declared
Road · Drinking water · Water supply · Sewage & drainage · Electricity · Fire fighting · Emergency evacuation · Solid waste · Rain-water harvesting · Renewable energy

Timeline

Building permit grantedOct 2020
Proposed completionDec 2022
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitCarpet sq m
1011ST FLOOR101.20
1021ST FLOOR92.06
1041ST FLOOR90.67
SPLIT DUPLEX1ST FLOOR254.70
3012ND FLOOR106.61
3022ND FLOOR97.25
3042ND FLOOR95.68
2013RD FLOOR106.91
2023RD FLOOR97.25
2043RD FLOOR95.69
SPLIT DUPLEX3RD FLOOR254.70
4014TH FLOOR106.61
4024TH FLOOR97.25
4034TH FLOOR95.68

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

JHARERA · Promoter registration

NIRMAAN CONSTRUCTIONS

ProprietorshipPromoter constitution
2Projects
1City
2020–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
30 homeson the public record across 2 projects
3,384 sq mbuilt-up filed

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

JHARERA · Registration filing
Address
RANI BAGAN,VILLAGE-BATRIATU,
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 515m away · 4 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 3.4 km · circular roadRailway line 4.6 kmRailway station 4.7km away (Namkom Railway Station)Limited bus connectivity nearby
Water & environment
Water body 892 m · Joda Talab
distances only — not a flood assessment
04

Planning authority

JHARERA · Approved building plan
Building Permitapproved 15 Oct 2020 · 5 yrs ago

The promised possession date (6 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — JHARERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — JHARERA does not publish a complaints register. This read cannot speak to them either way.