HORIZONMarkets
01

Complete project overview

JHARERA · Registration filing
Units
46 units
Carpet area
63–107 sq mper unit, as filed
Parking
51 spaces49 covered · 2 open
Amenities declared
Road · Drinking water · Water supply · Sewage & drainage · Electricity · Fire fighting · Emergency evacuation · Solid waste · Rain-water harvesting · Renewable energy · EV charging

Timeline

Building permit grantedSep 2021
Proposed completionFeb 2024
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitCarpet sq m
FLAT-1Ground105.74
FLAT-2Ground103.21
FLAT-3Ground82.80
FLAT-4Ground95.23
FLAT-5Ground90.39
FLAT-6Ground99.34
FLAT-1First98.09
FLAT-2First93.57
FLAT-3First101.56
FLAT-4First102
FLAT-5First63.39
FLAT-6First103.17
FLAT-7First107.26
FLAT-8First85.88
FLAT-9First94.13
FLAT-10First90.42
FLAT-1Second98.11
FLAT-2Second93.57
FLAT-3Second105.53
FLAT-4Second105.89
FLAT-5Second64.61
FLAT-6Second106.66
FLAT-7Second107.30
FLAT-8Second85.92
FLAT-9Second94.16
FLAT-10Second91.78
FLAT-1Third98.11
FLAT-2Third93.57
FLAT-3Third105.53
FLAT-4Third105.89
FLAT-5Third64.61
FLAT-6Third106.66
FLAT-7Third107.30
FLAT-8Third85.92
FLAT-9Third94.16
FLAT-10Third91.78
FLAT-1Fourth98.11
FLAT-2Fourth93.57
FLAT-3Fourth105.53
FLAT-4Fourth105.89
FLAT-5Fourth64.61
FLAT-6Fourth106.66
FLAT-7Fourth107.30
FLAT-8Fourth85.92
FLAT-9Fourth94.16
FLAT-10Fourth91.78

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

JHARERA · Promoter registration

RAJDEEP ESTATE DEVELOPERS

Partnership / LLPPromoter constitution
1Projects
1City
2021–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

JHARERA · Registration filing
District
Ranchi
Circle (Anchal)
Town
Village
LALPUR
Address
KUMHAR TOLI, LALPUR,
Plot no.
262
Khata no.
16
What’s nearby
Schools1 school within 1km · College or university 1.4km away
HealthcareHospital 152m away · 7 clinics within 1km · Pharmacy within 1km
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Mall 1.7km away · Bank 465m away
Getting around
Primary road 20 m · circular roadRailway line 1.8 kmRailway station 2.1km away (Ranchi)Limited bus connectivity nearby
Water & environment
Water body 1.0 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹7.50 Cr declared to build 46 flats. What that works out to:

₹16.30 Lakhdeclared cost per flatall-in — land + construction
₹1,592/sq ftof carpet area₹17,136/sq m

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

JHARERA · Approved building plan
Building Permitapproved 3 Sep 2021 · 4 yrs ago

The promised possession date (4 Feb 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — JHARERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — JHARERA does not publish a complaints register. This read cannot speak to them either way.