Ashford Regal - Phase III - Wing F Project

P51800048460 · MahaRERA · https://gethorizon.in/projects/ashford-regal-phase-iii-wing-f-project-kurla-i7dlk5dl

01

Complete project overview

MahaRERA · Registration filing
Project name
Ashford Regal - Phase III - Wing F Project
Units
55 units
Floors
41
Buildings
2
Parking
279 spaces
Land area
661 sq m

Timeline

RERA registeredJan 2023
Proposed completionDec 2025
TodaySep 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Internal finishes15%
Sewerage (Chamber,…15%
Stairs & lifts50%
Solid Waste Manage…60%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

WMI Real Estate Developers LLP

CompanyPromoter type
Mumbai City, MAHARASHTRABased in
5Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
972 homeson the public record across 5 projects
16,986 sq mbuilt-up filed
50,065 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from WMI Real Estate Developers LLP— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400078
Survey no.
358/11
North boundary
CTS Nos 358A - 2 and 358 - 1 -A - 3
East boundary
CEAT Tyre road
South boundary
Some Portion of CEAT Tyre road and some part of Ra
West boundary
CTS Nos 358A - 2 and 358 - 1 -A - 3
What’s nearby
SchoolsNearest school 1.0km away · College or university 1.1km away
HealthcareHospital 203m away · 6 clinics within 1km
Lifestyle1 park within 500m · Gym or sports centre 1.7km away · 13+ restaurants and cafes within 1km
ShoppingSupermarket 980m away · Mall 1.5km away · Convenience store within 500m
Getting around
Expressway 1.1 km · Eastern Express HighwayPrimary road 649 mRailway line 128 m · Central LineRailway station 390m away (Nahur)16 bus stops within 500m
Water & environment
Water body 726 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 358/11

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

5,108 residential projects still under way within 25 km. Step out ring by ring:

Of the 1,270 projects the radar draws within 6 km — every kind, every stage — 487 are residential projects still under way. This list keeps only those, and looks further out.

27 projects within 1 km — showing the nearest 6.

10 m awayOthers

Ashford Regal - Phase I - Wing A Project

WMI Real Estate Developers LLP · Kurla

Oct 2022registered
Jun 2027target completion
Scale295 flatsAuthorityMahaRERA
10 m awayOthers

Ashford Regal - Phase II - Wing B Project

WMI Real Estate Developers LLP · Kurla

Oct 2022registered
Dec 2027target completion
Scale295 flatsAuthorityMahaRERA
10 m awayMixed

Ashford Regal - Phase IV- Wing C Project

WMI Real Estate Developers LLP · Bhandup · Kurla

Oct 2024registered
Jun 2029target completion
Government Guidance Rate₹1,30,812/sq ydScale295 flatsAuthorityMahaRERA
10 m awayMixed

Ashford Regal – Phase V – Wing D Project

WMI Real Estate Developers LLP · Bhandup · Kurla

Mar 2026registered
Jun 2030target completion
Government Guidance Rate₹1,30,812/sq ydScale32 flatsAuthorityMahaRERA
210 m awayMixed

Shreeji Skyrise

Shreeji Lifespaces Realtech · Bhandup · Kurla

Sep 2025registered
Dec 2028target completion
Government Guidance Rate₹1,30,812/sq ydScale142 flatsAuthorityMahaRERA
240 m awayOthers

MARSHAL SRISHTI II

MARSHAL ENTERPRISES · Kurla

May 2023registered
Dec 2028target completion
Scale68 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.