HORIZONMarkets
01

Complete project overview

RERA Bihar · Registration filing
Units
168 units
Unit mix
132 × 3 BHK · 36 × 2 BHK
Buildings
2
Parking
216 spaces
Land area
7,181 sq m
Built-up area
17,960 sq m

Timeline

Project startedOct 2016
RERA registeredJun 2018
Proposed completionDec 2020
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

168 units across 10 batches
BuildingTypeArea sq mCount
Ashiana Green City Block A2 BHK1266
Ashiana Green City Block A2 BHK1096
Ashiana Green City Block A3 BHK3924
Ashiana Green City Block B & C2 BHK3124
Ashiana Green City Block B & C3 BHK3924
Ashiana Green City Block B & C3 BHK4024
Ashiana Green City Block B & C3 BHK3824
Ashiana Green City Block B & C3 BHK7512
Ashiana Green City Block B & C3 BHK9612
Ashiana Green City Block B & C3 BHK8512

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Bihar · Promoter registration

ASHIANA CREATORS PVT LTD

CompanyPromoter type
Patna, BiharBased in
---Select---Also RERA-registered in
2Projects
1Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
520 homeson the public record across 2 projects
49,507 sq mbuilt-up filed
19,832 sq mland declared
₹101.72 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Bihar · Registration filing
District
Patna
Anchal (block)
Danapur
Mauja (revenue village)
Mainpur
Address
MAUZA MAINPURA SHANKER, TAUZI-5234, THANA-24, KHATA-110,134,104,44,144
What’s nearby
SchoolsNo schools within 2km · Library 207m away
HealthcareHospital 406m away · 2 clinics within 1km
LifestylePark 538m away · Gym or sports centre 1.2km away
ShoppingSupermarket 1.1km away · Mall 56m away
Getting around
Expressway 501 mPrimary road 1.7 kmRailway line 3.0 kmRailway station 3.2km away (Patliputra)Limited bus connectivity nearby
Water & environment
Water body 1.2 kmRiver 1.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹36.12 Cr declared to build 168 flats. What that works out to:

₹21.50 Lakhdeclared cost per flatall-in — land + construction
₹1,868/sq ftof built-up area₹20,112/sq m
30%of the cost is land₹1,423/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Bihar · Approved building plan
Building Permit

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Bihar does not publish quarterly progress reports. How far along it actually is cannot be read here.