HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
58 units
Mix
36 × 2BHK · 22 × 3BHK
Booked
10 of 58 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
3,550 sq m
Floor area
8,573 sq m
Description
Ghazal Elysium

Timeline

Project startedJan 2026
RERA registeredJan 2026
Proposed completionJun 2029
TodayJul 2026
Construction progress

0% overall, as filed

Basement(s) and Plinth0%
Slabs of Super Structure0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation1%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

48 of 58 available
TypeArea sq mAvailable
3BHK11019 of 22
2BHK879 of 12
2BHK8811 of 12
2BHK849 of 12

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Ghazal Builders & Developers LLP

Limited Liability PartnershipPromoter type
Kozhikode, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
3Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
171 homeson the public record across 3 projects
25,757 sq mbuilt-up filed
9,364 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Chathamangalam Grama PanchayatGrama Panchayat1 of 3 projects
Kottakkal MunicipalityMunicipality1 of 3 projects
Kozhikode Municipal CorporationMunicipal Corporationthis project1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Moozhikkal
Village
CHELAVUR
Taluk
Kozhikode
District
Kozhikode
Pincode
673571
Survey no.
22/33,22/34,22/35,22/36,22/37,22/93,22/107
Patta no.
4276, 13612
What’s nearby
Schools1 school within 500m · College or university 1.1km away · Library 1.3km away
HealthcareHospital 1.3km away
LifestyleNo parks within 2km · Playground within 500m · Gym or sports centre 293m away
ShoppingSupermarket 166m away · Bank 877m away · ATM within 500m
Getting around
Expressway 168 m · Wayanad RoadPrimary road 1.5 km · Palakottuvayal-Mundikal Thayam RoadNo metro or railway within 5km6 bus stops within 500m
Water & environment
River 257 m · Poonoor RiverCanal 609 mWater body 897 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kozhikode Municipal Corporation

Municipal Corporation
approved 21 Nov 2025 · 8 mo ago
Building Permit no. BP/125827/2025Survey no. 22/33,22/34,22/35,22/36,22/37,22/93,22/107
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BP/125827/2025 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kozhikode Municipal Corporation

Municipal corporation / municipality

Has approved 57 RERA projects3.7% of Kerala.

an apartments market96% apartments · 4% plotted layouts. Apartments like yours are this body's core business.

Builders
36
On record
3,822 flats · 80 plots
Since
2021

More apartment-heavy than Kerala overall — 96% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.