RAJ-RERA · Registration filing
Land area
1,128 sq m
Completion deadline extended
1 extension on record — latest to 28 Feb 2019declared reason: other than force majeure

Timeline

Construction startFeb 2014
RERA registeredDec 2017
Proposed completionFeb 2018
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

SHRI HANUMANT REAL ESTATE

OrganisationPromoter type
Sikar, RajasthanBased in
1Projects
1City
2017–2018Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Ward No. 17, Bagpath colony ke pass,Devipura,Sikar, Sikar, Sikar, Sikar, 332001
Village
Sikar
Taluka
Sikar
District
Sikar
Pincode
332001
What’s nearby
SchoolsNearest school 1.8km away · College or university 1.6km away · Library 1.6km away
HealthcareHospital 553m away · Clinic within 2km
LifestylePark 828m away · Gym or sports centre 1.8km away
ShoppingSupermarket 226m away · Mall 1.2km away · Bank 715m away
Getting around
Expressway 2.4 km · Sikar Bypass RoadPrimary road 341 mRailway line 2.0 kmRailway station 2.0km away (Sikar Railway Station)Limited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹3.12 Cr declared. What that works out to:

13%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Nagar Parishad

Municipal Council
Building Permitapproved 14 Dec 2017 · 8 yrs ago

The promised possession date (28 Feb 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal body

A Nagar Nigam / Parishad / Palika that sanctions within its own town limits. It has approved 358 RERA projects across 29 districts about 1 in 6 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.