Complete project overview

K-RERA · Registration filing
Units
31 units
Mix
31 × 4BHK
Booked
13 of 31 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,475 sq m
Floor area
12,432 sq m
Description
SFS LA FORTUNA

Timeline

Project startedSep 2024
RERA registeredSep 2024
Proposed completionNov 2028
TodayJul 2026
Construction progress

13% overall, as filed

Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Slabs of Super Structure10%
Basement(s) and Plinth80%
Excavation100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

18 of 31 available
TypeArea sq mAvailable
4BHK16512 of 16
4BHK1986 of 15

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

SKYLINE FOUNDATIONS AND STRUCTURES PRIVATE LIMITED

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
20Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,365 homeson the public record across 20 projects
3,14,832 sq mbuilt-up filed
71,203 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thiruvananthapuram Municipal CorporationMunicipal Corporation6 of 20 projects
Thrikkakara MunicipalityMunicipalitythis project5 of 20 projects
Andoorkonam Grama PanchayatGrama Panchayat3 of 20 projects
Karakulam Grama PanchayatGrama Panchayat1 of 20 projects
Kochi Municipal CorporationMunicipal Corporation1 of 20 projects
MunicipalityLocal body (LSGI)1 of 20 projects
ThrikkakaraLocal body (LSGI)1 of 20 projects
Thrikkakara Municipality ErnakulamLocal body (LSGI)1 of 20 projects
Tripunithura MunicipalityMunicipality1 of 20 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Kollamkudimugal Road
Village
KAKKANAD
Taluk
Kanayannur
District
Ernakulam
Pincode
682021
Survey no.
546/4-2
Patta no.
23363
What’s nearby
Schools3 schools within 1km · 5 educational institutions within 1km · Library 852m away
HealthcareHospital 802m away · 2 clinics within 1km · Pharmacy within 1km
LifestylePark 886m away · Gym or sports centre 860m away · 15+ restaurants and cafes within 1km
ShoppingSupermarket 439m away · Mall 201m away · Convenience store within 1km
Getting around
Expressway 3.3 km · Salem - Kochi - Kanyakumari HighwayPrimary road 888 m · Palarivattom - Kakkanad RoadRailway line 3.7 kmMetro station 3.2km away (InfoPark I Station)Bus stop within 1km
Water & environment
Water body 137 mCanal 616 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thrikkakara Municipality

Municipality
approved 20 Jul 2024 · 2 yrs ago
Building Permit no. BP/6637/2024Survey no. 546/4-2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BP/6637/2024 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Thrikkakara Municipality

Municipal corporation / municipality

Has approved 60 RERA projects3.9% of Kerala.

an apartments market92% apartments · 8% plotted layouts. Apartments like yours are this body's core business.

Builders
33
On record
4,257 flats · 86 plots
Since
2021

More apartment-heavy than Kerala overall — 92% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.