TN/29/Building/0326/2024

TN/29/Building/0326/2024 · TNRERA · https://gethorizon.in/projects/tn-29-building-0326-2024-sy269eto

01

Complete project overview

TNRERA · Registration filing
Description
ARA VINESH ENCLAVE Residential building consisting of 2 Blocks, Block A- Stilt Floor + 5 Floors (Height - 18.30 m) with 25 Dwelling units, Block B - Stilt Floor + 5 Floors (Height - 18.30 m) with 30 Dwelling units totally 55 dwelling units with availing premium FSI at T Ponnambalam Salai, Kulapakkam, Chennai comprised in S.No. 116/2 of Kulapakkam village within the limits of Kundrathur Panchayat union Chennai District.
Registration no.
TN/29/Building/0326/2024

Timeline

RERA registeredApr 2024
Proposed completionDec 2025
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

ARA CONSTRUCTION

ARA CONSTRUCTIONPromoter
3Projects
1Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3 projectson the public record across 3 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from ARA CONSTRUCTION— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.4km away · Clinic within 2km · Pharmacy within 500m
LifestyleNo parks within 2km
ShoppingSupermarket 689m away
Getting around
Expressway 1.8 km · Chennai Bypass ExpresswayPrimary road 1.2 km · Kodambakkam – Sriperumbudur RoadRailway line 3.8 kmMetro station 3.6km away (Chennai International Airport)Limited bus connectivity nearby
Water & environment
Water body 712 m
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

CMDA (Chennai Metropolitan Development Authority)

CMDA (Chennai Metropolitan Development Authority)
approved 4 Apr 2024 · 2 yrs ago
Planning Permission no. OL-PP/NHRB/0107/2023

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan OL-PP/NHRB/0107/2023 on the approving authority’s portal to confirm the approval.

The approving body, at scale

CMDA (Chennai Metropolitan Development Authority)

Metropolitan development authority

Has approved 1,914 RERA projectsabout 1 in 2 in Tamil Nadu, more than any other body in the state.

Builders
1,310
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

485 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 95 projects the radar draws within 6 km — every kind, every stage — 76 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

3 projects within 1 km — showing the nearest 3.

420 m away

ARA VINESH ENCLAVE

ARA Construction

Jul 2026registered
Apr 2027target completion
AuthorityTNRERA
700 m away

THE BANYAN

ANAND DEVELOPERS

Jan 2025registered
Jan 2028target completion
AuthorityTNRERA
890 m away

GPB’s NIDHULAN PARK VIEW CASTLE

GPB BUILDERS & PROMOTERS PROVATE LIMITED

Dec 2024registered
Feb 2031target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.